#440
by
Chris Bergin
on 06 Jun, 2007 01:29
-
-
#441
by
James Lowe1
on 06 Jun, 2007 04:38
-
As per L2:
Constraint Status: CAT I: 0 CAT II: 76 (down from 105 on Monday).
CAT I's are show stoppers. CAT II are IPRs etc. We'll update this tomorrow.
-
#442
by
ShuttleDiscovery
on 06 Jun, 2007 06:49
-
-
#443
by
DaveS
on 06 Jun, 2007 13:54
-
L-2 Countdown Status Briefing coming up on NASA TV Media Channel at 10 am EDT. Following the briefing, you could switch over to the Public channel and watch the Expedition Russian EVA#2.
-
#444
by
Avron
on 06 Jun, 2007 14:01
-
No significant issues... all tracking well
-
#445
by
Avron
on 06 Jun, 2007 14:02
-
10:30PM tomorrow for RSS retract
-
#446
by
Avron
on 06 Jun, 2007 14:04
-
Countdown is exceptional
-
#447
by
Avron
on 06 Jun, 2007 14:07
-
Look like the storms will form west of the pad Firday..
Tanking.. no issues zero %
Launch --- 30 % of WX issues
-
#448
by
Avron
on 06 Jun, 2007 14:08
-
Tals -- all look good..
Sat launch - 40% - TS..
48 hours --- 40%.. more issues at TALS
-
#449
by
psloss
on 06 Jun, 2007 14:13
-
Good question from Mark about weather issues with the PRSD load...
-
#450
by
Avron
on 06 Jun, 2007 14:16
-
4pm next for L-2 review
One issue.. STS-118 flanges etc..
RCC - no impacts on STS-117 -- closed out.
-
#451
by
Avron
on 06 Jun, 2007 14:19
-
Winds only WX issue today - 50 kts...
Next post L-2 --- they think 3:30 to 4pm range...
Very clean
-
#452
by
psloss
on 06 Jun, 2007 14:21
-
Avron - 6/6/2007 10:16 AM
One issue.. STS-118 flanges etc..
RCC - no impacts on STS-117 -- closed out.
Those are noted on L2 -- not sure if they've finished discussions, since the L-2 review is still upcoming this afternoon.
Edit: we'll probably find out afterwards about whether the PRSD load was held up -- it will depend on what the weather is like when they get there in the timeline...I didn't catch what Kathy Winters said about possible lightning advisories later today, but that's part of what held up some of the loads during the summer launch counts last year...
-
#453
by
DaveS
on 06 Jun, 2007 14:34
-
psloss - 6/6/2007 4:21 PM
Edit: we'll probably find out afterwards about whether the PRSD load was held up -- it will depend on what the weather is like when they get there in the timeline...I didn't catch what Kathy Winters said about possible lightning advisories later today, but that's part of what held up some of the loads during the summer launch counts last year...
If they got any Phse 2's prior to starting PRSD load activties, they would stop. If they got any Phase's during the loadings, they would not stop the loadings.
-
#454
by
Chris Bergin
on 06 Jun, 2007 14:50
-
We're working through the ET-117/MPS disconnect issue on L2 (meeting is ongoing right now), but will be writing an article on this for those not on L2.
-
#455
by
DaveS
on 06 Jun, 2007 17:00
-
Now at T-27 hours and holding.
-
#456
by
Chris Bergin
on 06 Jun, 2007 17:05
-
Chris Bergin - 6/6/2007 3:50 PM
We're working through the ET-117/MPS disconnect issue on L2 (meeting is ongoing right now), but will be writing an article on this for those not on L2.
No resolution via pre-brief, now being debated by MMT.
Flight rationale is always favorite. The flip side is a delay of several days. We're following.
-
#457
by
TFGQ
on 06 Jun, 2007 17:45
-
count will be picked up at 630 pm instead of 5 pm
-
#458
by
psloss
on 06 Jun, 2007 17:51
-
TFGQ - 6/6/2007 1:45 PM
count will be picked up at 630 pm instead of 5 pm
Any reason for the delay? Catching up on timeline?
Thanks.
-
#459
by
TFGQ
on 06 Jun, 2007 17:54
-
i know a person in the newsroom they informed me about this