Chris Bergin - 13/7/2007 11:57 AMLatest on Discovery's processing:http://www.nasaspaceflight.com/content/?cid=5166SSME installation this weekend.
George CA - 15/7/2007 5:18 AMQuoteChris Bergin - 13/7/2007 11:57 AMLatest on Discovery's processing:http://www.nasaspaceflight.com/content/?cid=5166SSME installation this weekend.Any word on how Engine installation is proceeding?
shuttlefan - 16/7/2007 3:28 PM What day this week does SRB stacking begin?
From L2:"Ø STS-120/BI-131/RSRM 98 SRB Stacking (H/B-1) Activities: v LAB Preps/Lift into H/B-1 & Mate to MLP is scheduled for Wednesday (07/18). "
Chris Bergin - 15/7/2007 4:14 PMQuoteGeorge CA - 15/7/2007 5:18 AMQuoteChris Bergin - 13/7/2007 11:57 AMLatest on Discovery's processing:http://www.nasaspaceflight.com/content/?cid=5166SSME installation this weekend.Any word on how Engine installation is proceeding?I'll ask..
Endeavour118 - 17/7/2007 8:47 PMwhen will srb and et mating start?
One of the payloads for STS-120, the MBSU for the station's electrical system, has already been installed in Discovery's payload bay. Photos of the operation can be seen in KSC Media Gallery: http://mediaarchive.ksc.nasa.gov/search.cfm?cat=4
eeergo - 20/7/2007 6:15 PMOne of the payloads for STS-120, the MBSU for the station's electrical system, has already been installed in Discovery's payload bay. Photos of the operation can be seen in KSC Media Gallery: very nice.. three guys working.. 13 managing and one taking pics.. tax dollars hard at work..
One of the payloads for STS-120, the MBSU for the station's electrical system, has already been installed in Discovery's payload bay. Photos of the operation can be seen in KSC Media Gallery: very nice.. three guys working.. 13 managing and one taking pics.. tax dollars hard at work..