Hubble sat in storage for four years with that flaw. Another case of years of opportunity, and inadequate testing.
Not possible to test in the spacecraft configuration. Testing had to be done on the mirror. Don't even know if testing was feasible in the telescope configuration.
The additional four years would have made no difference. Two existing refractive null correctors had already demonstrated the fault in the HST primary mirror BEFORE the mirror was built into the optical assembly. However, the new Reflective Null Corrector that Perkin-Elmer had constructed specially for Hubble, showed NO error.
Perkin-Elmer willingly chose to ignore the results from the existing refractive null correctors: they believed that only their new Reflective Null Corrector was telling "the truth".
However, after STS-31 the fault in Hubble's primary mirror was traced all the way back to a design error in Perkin-Elmer's new Reflective Null Corrector.
The results from the older refractive null correctors turned out to have been correct all the time.
Summarizing: the fault in Hubble's primary mirror was known AND confirmed at an early stage. But Perkin-Elmer believed those measurement results themselves to be faulty. Any additional testing in the "storage" years would not have changed that attitude.
But I digress.
P-E didn't have the experience that Kodak had having built over 70 mirrors including those for the KH-11s, but P-E submitted the lower bid wanting to develop the skillset. P-E's equipment had a measuring point with a protective cap to prevent it from damage, and the measurements were made to the cap instead of to the measuring point itself leading to a 2mm error. (I don't think this was ever reported) In the end, Kodak's mirror team were brought in to figure out P-E's problem. One benefit was that during the delays, there had been so much advancement in digital camera technology, that the replacement optics package was really an enhancement. At one point P-E must have realized that they were in over their heads since they subcontracted Kodak to build a backup mirror, which didn't have the flaw and is the one now on display. P-E never ran end-to-end tests or even compared the two mirrors and instead relied on their machine that built the mirror to test the mirror. So another example of failure due to lack of end-to-end and independent testing and why the engineers doing the testing should be as qualified and empowered as those doing the development.
Hubble sat in storage for four years with that flaw. Another case of years of opportunity, and inadequate testing.Not possible to test in the spacecraft configuration. Testing had to be done on the mirror. Don't even know if testing was feasible in the telescope configuration.
However, after STS-31 the fault in Hubble's primary mirror was traced all the way back to a design error in Perkin-Elmer's new Reflective Null Corrector.
P-E didn't have the experience that Kodak had having built over 70 mirrors including those for the KH-11s, but P-E submitted the lower bid wanting to develop the skillset. P-E's equipment had a measuring point with a protective cap to prevent it from damage, and the measurements were made to the cap instead of to the measuring point itself leading to a 2mm error. (I don't think this was ever reported) In the end, Kodak's mirror team were brought in to figure out P-E's problem. One benefit was that during the delays, there had been so much advancement in digital camera technology, that the replacement optics package was really an enhancement. At one point P-E must have realized that they were in over their heads since they subcontracted Kodak to build a backup mirror, which didn't have the flaw and is the one now on display. P-E never ran end-to-end tests or even compared the two mirrors and instead relied on their machine that built the mirror to test the mirror. So another example of failure due to lack of end-to-end and independent testing and why the engineers doing the testing should be as qualified and empowered as those doing the development.What I read said that the design was correct, but the technician assembling the null corrector got a spacer in the incorrect location. The null corrector was never physically tested against its specs. That was in a book I lent out and never got back; Amazon searches give me only books that are much more recent than the one I had, so I can't quote it exactly.
I remember reading about this exactly as described in sky and telescope. So it was reported.
)
On the other hand,
NASA's Discovery Mission Kepler made the choice that only full system testing could verify the optical functionality of its Schmidt imager.
The thermal vacuum testing wound up costing the equivalent of another Discovery mission.
And, by the time Kepler did uncover a hardware issue, they were so far over budget that they were instructed to live with it, which is why the primary mission period was shortened from five years to three.
There is such a thing as too much hardware testing.
Can we please get back on topic here? The piecewise vs. end-to-end testing is very interesting, but not here.
P-E didn't have the experience that Kodak had having built over 70 mirrors including those for the KH-11s, but P-E submitted the lower bid wanting to develop the skillset. P-E's equipment had a measuring point with a protective cap to prevent it from damage, and the measurements were made to the cap instead of to the measuring point itself leading to a 2mm error. (I don't think this was ever reported) In the end, Kodak's mirror team were brought in to figure out P-E's problem. One benefit was that during the delays, there had been so much advancement in digital camera technology, that the replacement optics package was really an enhancement. At one point P-E must have realized that they were in over their heads since they subcontracted Kodak to build a backup mirror, which didn't have the flaw and is the one now on display. P-E never ran end-to-end tests or even compared the two mirrors and instead relied on their machine that built the mirror to test the mirror. So another example of failure due to lack of end-to-end and independent testing and why the engineers doing the testing should be as qualified and empowered as those doing the development.
I remember reading about this exactly as described in sky and telescope. So it was reported.
Just realized I never posted the excerpts I started putting together yesterday.QuoteIn addition, the CCP and ISS programs are concerned that operational staff may not be able to safely operate Boeing’s crewed spacecraft if there are any issues with Boeing’s flight software. CCP reported that Boeing’s approach to software development and testing created a significant backlog of software problem reports. Program officials said the operations team is being trained on operational workarounds to complete functions manually that software would normally automate. Several teams reported little capacity to safely accommodate additional operational workload that may be needed if there are any problems with Boeing’s flight software. To mitigate this issue, CCP plans to provide operational teams 6 months of training time with released software and closely monitor workload.
Interesting thing I noticed. Boeing does not seem to have an FAA Commercial Re-entry License for the CST-100:
https://www.faa.gov/data_research/commercial_space_data/licenses/
Does the fact that its for NASA remove the need for such a license?
Interesting thing I noticed. Boeing does not seem to have an FAA Commercial Re-entry License for the CST-100:
https://www.faa.gov/data_research/commercial_space_data/licenses/
Does the fact that its for NASA remove the need for such a license?
NASA wouldn't be able to do this. Anything that flies through airspace is subject to the FAA.
NASA wouldn't be able to do this. Anything that flies through airspace is subject to the FAA.
Not true. Goverment managed launches like SLS or ICBMs are not managed by FAA licensing. The FAA is given notice for a need to close airspace.
NASA wouldn't be able to do this. Anything that flies through airspace is subject to the FAA.
Not true. Goverment managed launches like SLS or ICBMs are not managed by FAA licensing. The FAA is given notice for a need to close airspace.Well, military is obviously a different thing altogether, but doesn't SLS and all other rocket launches still need a launch license?
NASA wouldn't be able to do this. Anything that flies through airspace is subject to the FAA.
Not true. Goverment managed launches like SLS or ICBMs are not managed by FAA licensing. The FAA is given notice for a need to close airspace.Well, military is obviously a different thing altogether, but doesn't SLS and all other rocket launches still need a launch license?
No, not Government managed launches like SLS or ICBMs or Titan IVs