Has the STS-117 (LON for STS-116) ET had its ECO sensors replaced in light of the problems on STS-114 and also STS-115?
-
#81
by
punkboi
on 26 Oct, 2006 19:26
-
FransonUK - 25/10/2006 11:07 PM ECO's are dirty initials to mention 
I thought they were called Launch Delay Systems...according to a post-launch briefing for STS-115?
-
#82
by
nathan.moeller
on 26 Oct, 2006 20:19
-
punkboi - 26/10/2006 2:09 PM
FransonUK - 25/10/2006 11:07 PM ECO's are dirty initials to mention 
I thought they were called Launch Delay Systems...according to a post-launch briefing for STS-115?
I believe our administrator's term for them was "LPDs" - Launch Prevention Devices
-
#83
by
punkboi
on 27 Oct, 2006 20:45
-
nathan.moeller - 26/10/2006 1:02 PM punkboi - 26/10/2006 2:09 PM FransonUK - 25/10/2006 11:07 PM ECO's are dirty initials to mention 
I thought they were called Launch Delay Systems...according to a post-launch briefing for STS-115?
I believe our administrator's term for them was "LPDs" - Launch Prevention Devices 
Ah- There you go. That sounds even, um, better 
-
#84
by
Chris Bergin
on 03 Nov, 2006 13:32
-
STS 117 / OV104 in OPF 1
Power is up.
Power up Friday 0700.
V5D09 OMS preps for manifold drain and thruster removal and replacement in work.
APU preps for manifold drain and transducer removal and replacement in work.
-
#85
by
Chris Bergin
on 03 Nov, 2006 13:38
-
Slide from Nov 2 PRCB processing latest (taken from L2 presentation)
-
#86
by
dutch courage
on 03 Nov, 2006 15:36
-
ET/SRB Mate, Closeout (RED) ET/SRB Mate on 1/19/06, Red for contingency.
Should this date be 1/19/07 (a year later), Chris?
-
#87
by
Chris Bergin
on 04 Nov, 2006 22:36
-
dutch courage - 3/11/2006 4:19 PM
ET/SRB Mate, Closeout (RED) ET/SRB Mate on 1/19/06, Red for contingency.
Should this date be 1/19/07 (a year later), Chris?
No wonder it's red

Yes, but NASA made the mistake on the document.
-
#88
by
Chris Bergin
on 04 Nov, 2006 22:36
-
dutch courage - 3/11/2006 4:19 PM
ET/SRB Mate, Closeout (RED) ET/SRB Mate on 1/19/06, Red for contingency.
Should this date be 1/19/07 (a year later), Chris?
No wonder it's red

Yes, but NASA made the mistake on the document.
-
#89
by
Chris Bergin
on 04 Nov, 2006 22:36
-
STS 117 / OV104 / OPF 1
Orbiter powered up supporting APU3 transducer R&R
SCAPE operations in progress
-
#90
by
Andy L
on 05 Nov, 2006 04:57
-
What is SCAPE?
-
#91
by
Davie OPF
on 05 Nov, 2006 05:44
-
Andy L - 4/11/2006 11:40 PM
What is SCAPE?
Self-Contained Atmospheric Protection Ensemble
-
#92
by
Chris Bergin
on 05 Nov, 2006 18:19
-
STS 117 / OV104 / OPF 1
Orbiter powered up supporting APU3 transducer R&R
SCAPE operations in progress
-
#93
by
Chris Bergin
on 06 Nov, 2006 15:17
-
STS 117 / OV104 / OPF 1
Orbiter system test
Lockbolt R&R in work
Nosecap RCC repair in work
Chin panel fit check
Baseline Y inspections in work
ECO sensor mod is in work
Thrust and APU transducer R&R is complete. SCAPE
WSB checkout and servicing in work
-
#94
by
Chris Bergin
on 06 Nov, 2006 20:31
-
STS 117 / OV104 / OPF 1
Lockbolt R&R in work
Nosecap RCC repair in work
Chin panel fit check
-
#95
by
Chris Bergin
on 07 Nov, 2006 04:13
-
STS 117 / OV104 / OPF 1
Integrated drag chute ops in work
Payload bay door rigging in work
Power up Tuesday 08:00
-
#96
by
Chris Bergin
on 08 Nov, 2006 18:00
-
STS 117 / OV104 / OPF 1
Orbiter power system validation complete
Lock bolt R&R in work
Chin panel fit check in work
Baseline Y inspections in work
WSB checkout and servicing in work
Integrated drag chute installation in work
NH3 servicing preps in work.
Tile operations in work
Fuel cell 1 R&R in work
Thruster R&R preps in work
-
#97
by
Chris Bergin
on 08 Nov, 2006 23:19
-
STS 117 / OV104 / OPF 1
Power is up through Sunday 11/12
OMS manifold drain ops in work.
(Unknown) for the hazardous portion 05:00 Saturday
-
#98
by
shuttlefan
on 09 Nov, 2006 00:21
-
Hi, Chris!! Have they installed the SSMEs on Atlantis yet and do you know when they plan to begin SRB stacking?
-
#99
by
Chris Bergin
on 09 Nov, 2006 01:37
-
shuttlefan - 9/11/2006 1:04 AM
Hi, Chris!! Have they installed the SSMEs on Atlantis yet and do you know when they plan to begin SRB stacking?

Hi Shuttlfan!!

No idea, I've lost track due to Shuttle overload. I'll ask and find out (any Atlantis OPF engineers on here are welcome to beat me to it).