#140
by
Chris Bergin
on 02 Dec, 2006 22:12
-
STS 117 / OV104 / OPF 1
Powered up through second shift
Panel buildup in work
-
#141
by
Chris Bergin
on 03 Dec, 2006 16:28
-
STS 117 / OV104 / OPF 1
Orbiter powered down
-
#142
by
Chris Bergin
on 03 Dec, 2006 21:46
-
STS 117 / OV104 / OPF 1
Next scheduled vehicle power 1st shift Monday
-
#143
by
Chris Bergin
on 04 Dec, 2006 03:30
-
STS 117 / OV104 / OPF 1
Powered down
Next scheduled power up 08:00 Monday
VAB High Bay 1
Left aft booster is due for delivery in the transfer aisle 3rd shift Monday
-
#144
by
Chris Bergin
on 05 Dec, 2006 02:35
-
STS 117 / OV104 / OPF 1
Powered up
Power up Tuesday 06:00
SSME installation in work
Left aft booster preps for stacking in the VAB for STS 117 in work.
-
#145
by
rosbif73
on 05 Dec, 2006 14:11
-
Chris Bergin - 5/12/2006 4:18 AM
SSME installation in work
Left aft booster preps for stacking in the VAB for STS 117 in work.
Presumably that's an SSME we can see here - the backlit image makes it hard to see much...
-
#146
by
Chris Bergin
on 05 Dec, 2006 14:34
-
STS 117 / OV104 / OPF 1
Powered up
Power up Tuesday 06:00
SSME installation in work
-
#147
by
Chris Bergin
on 05 Dec, 2006 18:02
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Wing carry through complete
Mid seal in work
Chin panel blanket buildup in work
Baseline wire inspection in work
Tile operations in work
APU leak & functional is complete to date
SSME installation in work
Elevon rigging in work
-
#148
by
Chris Bergin
on 05 Dec, 2006 18:02
-
STS 117 / ET SRB / VAB
STS 117 SRB stacking in work
-
#149
by
Chris Bergin
on 05 Dec, 2006 19:58
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel blanket buildup in work
Baseline wire inspection in work
Tile operations in work
APU leak & functional is complete to date
SSME installation in work
Elevon rigging in work
-
#150
by
Chris Bergin
on 05 Dec, 2006 19:58
-
STS 117 / ET SRB / VAB
STS 117 SRB stacking in work
Left aft booster complete and stacked
Left aft center is in work
-
#151
by
Chris Bergin
on 08 Dec, 2006 02:25
-
OV-104 (STS-117)
? 86 tile cavities left-47 bonded to date
? Last week’s IPR on left-hand vent door #6-have isolated problem down to a 128-pin connector that had a loose pin in it. This will be repaired, and the IPR will go away.
? Completed ET door functional. Went into jack transport and installed main landing gear tires. Working on tile around the main landing gear doors and completed jack transfer.
-
#152
by
Josheyman
on 09 Dec, 2006 06:10
-
Which crew members would fly the STS-317 mission should it be required?
-
#153
by
anik
on 09 Dec, 2006 07:56
-
Josheyman - 9/12/2006 9:53 AM
Which crew members would fly the STS-317 mission should it be required?
Sturckow, Archambault, Swanson, Reilly (according to document at L2 section)...
-
#154
by
Orbiter Obvious
on 11 Dec, 2006 04:19
-
When will Atlantis be stood down from LON requirement?
-
#155
by
Avron
on 11 Dec, 2006 04:41
-
Orbiter Obvious - 11/12/2006 12:02 AM
When will Atlantis be stood down from LON requirement?
Need to wait for the MMT on that.. todays scans and tomorrows RPM images will need to be assessed first..
-
#156
by
Chris Bergin
on 11 Dec, 2006 11:08
-
Yeah, on 115 it was about FD5.
-
#157
by
Chris Bergin
on 12 Dec, 2006 02:30
-
STS 117 / OV104 / OPF 1
Powered up
Integrated hydraulic ops in work
VAB High Bay 1
Left forward stacking operations in work
-
#158
by
shuttlefan
on 12 Dec, 2006 13:44
-
Chris Bergin - 11/12/2006 9:13 PM
STS 117 / OV104 / OPF 1
Powered up
Integrated hydraulic ops in work
VAB High Bay 1
Left forward stacking operations in work
Hey Chris!! Have you heard whether or not all three SSMEs have been installed on Atlantis?
-
#159
by
Chris Bergin
on 12 Dec, 2006 19:25
-
Yep. She has her engines

STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Chin panel blanket buildup gap filler fabrication in work
Tile operations in work
SSME leak checks complete
SSME MPS integrated checks post SSME installations in work
Elevon rigging in work
Panel M010W testing in work
OME heat shield installation in work
Preps for CEIT in work
Integrated hydraulic operations flight controls complete
Star tracker retest complete