#120
by
Chris Bergin
on 25 Nov, 2006 22:32
-
STS 117 / OV104 / OPF 1
Orbiter powered down
Next power up 1st shift Monday the 27th.
-
#121
by
shuttlefan
on 26 Nov, 2006 02:01
-
I believe Atlantis will get her main engines in about a week, about the same time SRB stacking on the MLP is set to begin. Full speed ahead for the Shuttle Program!!
-
#122
by
Chris Bergin
on 27 Nov, 2006 16:08
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel fit check in work
Baseline wire inspections in work
Tile operations in work
Manifold backfill completed
MPS Delta P transducer removal in work
-
#123
by
mainengine
on 27 Nov, 2006 21:04
-
shuttlefan - 25/11/2006 8:44 PM
I believe Atlantis will get her main engines in about a week, about the same time SRB stacking on the MLP is set to begin. Full speed ahead for the Shuttle Program!!
Dec 5 according to processing schedules.
-
#124
by
shuttlefan
on 28 Nov, 2006 01:16
-
mainengine - 27/11/2006 3:47 PM
shuttlefan - 25/11/2006 8:44 PM
I believe Atlantis will get her main engines in about a week, about the same time SRB stacking on the MLP is set to begin. Full speed ahead for the Shuttle Program!!
Dec 5 according to processing schedules.
Hi, mainengine! Do you mean Dec.5th for both SSME installation and start of SRB stacking?
-
#125
by
nathan.moeller
on 28 Nov, 2006 04:34
-
shuttlefan - 27/11/2006 7:59 PM
mainengine - 27/11/2006 3:47 PM
shuttlefan - 25/11/2006 8:44 PM
I believe Atlantis will get her main engines in about a week, about the same time SRB stacking on the MLP is set to begin. Full speed ahead for the Shuttle Program!!
Dec 5 according to processing schedules.
Hi, mainengine! Do you mean Dec.5th for both SSME installation and start of SRB stacking? 
Last I read SRB stacking was scheduled to begin on the 4th of December with the SSME installation starting on the 5th.
-
#126
by
Chris Bergin
on 28 Nov, 2006 11:14
-
STS 117 / OV104 / OPF 1
Power is up
Power up Tuesday 08:00
FRCS functional preps in work
Star tracker door ops in work
-
#127
by
shuttlefan
on 28 Nov, 2006 12:53
-
nathan.moeller - 27/11/2006 11:17 PM
shuttlefan - 27/11/2006 7:59 PM
mainengine - 27/11/2006 3:47 PM
shuttlefan - 25/11/2006 8:44 PM
I believe Atlantis will get her main engines in about a week, about the same time SRB stacking on the MLP is set to begin. Full speed ahead for the Shuttle Program!!
Dec 5 according to processing schedules.
Hi, mainengine! Do you mean Dec.5th for both SSME installation and start of SRB stacking? 
Last I read SRB stacking was scheduled to begin on the 4th of December with the SSME installation starting on the 5th.
thanks Nathan!
-
#128
by
mainengine
on 28 Nov, 2006 13:07
-
Hi,
Last Shuttle Standup speaks of Main engine installation on Dec 4. Engines are usually installed on two days running I believe. So the'd be ready on Dec 5.
Don't know about srb stacking. sorry.
-
#129
by
Chris Bergin
on 28 Nov, 2006 15:34
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel adjust fit check in work
Baseline Y inspections in work
Tile operations in work
MPS Delta p transducer removal CTD transducer removed
ET door functional checks tile critical path in work
-
#130
by
Chris Bergin
on 28 Nov, 2006 15:36
-
mainengine - 28/11/2006 1:50 PM
Hi,
Last Shuttle Standup speaks of Main engine installation on Dec 4. Engines are usually installed on two days running I believe. So the'd be ready on Dec 5.
Don't know about srb stacking. sorry.
Nov 27 Standup/Integration report on L2 has:
"OV-104 (STS-117)
SRB stacking planned to start December 4th. "
-
#131
by
Chris Bergin
on 28 Nov, 2006 23:28
-
STS 117 / OV104 / OPF 1
Powered up
V1181 FRCS functional checkout scheduled for second shift tonight
-
#132
by
Chris Bergin
on 29 Nov, 2006 12:21
-
STS 117 / OV104 / OPF 1
Powered up
V1181 FRCS functional checkout in work
-
#133
by
Chris Bergin
on 29 Nov, 2006 16:47
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel adjust fit check in work
Baseline wire inspections in work
Tile operations in work
ET door functional preps tile critical path in work
OBSS sensor pack IVTs in work
FRCS functional and checkout 2 in work
-
#134
by
Chris Bergin
on 29 Nov, 2006 21:00
-
STS 117 / OV104 / OPF 1
Orbiter powered up through second
Next power up Thursday 08:00
-
#135
by
Chris Bergin
on 30 Nov, 2006 16:50
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel adjust fit check in work
Baseline wire inspections in work
Tile operations in work
ET door functional preps tile critical paths complete
ET door functional starts today
OBSS Insert pack IVTs in work
FRCS functional and checkout 1 2 in work
APU leak and functional starts today
WCS functional starts today
-
#136
by
Chris Bergin
on 30 Nov, 2006 23:24
-
STS 117 / OV104 / OPF 1
Orbiter powered up through second
Next power up Friday 08:00
-
#137
by
Chris Bergin
on 01 Dec, 2006 22:33
-
STS 117 / OV104 / OPF 1
Orbiter power system testing in work
Lockbolt R&R in work
Chin panel adjust fit check in work
Baseline wire inspections in work
Tile operations in work
ET door functional starts today
OBSS sensor pack IVTS in work
FRCS functional and checkout 1 2 is complete
APU leak and functional in work
WCS functional in work
Integrated hydraulic ops flight control testing complete
-
#138
by
Chris Bergin
on 02 Dec, 2006 03:23
-
STS 117 / OV104 / OPF 1
Orbiter powered up through second shift
Next power up Saturday 08:00
Ammonia vent evacuation in work through second
-
#139
by
Chris Bergin
on 02 Dec, 2006 17:34
-
STS 117 / OV104 / OPF 1
Orbiter power 1st shift to support APU leak and functional
Chin panel X-ray ops complete