The Vandenberg pad is just as new as LC-39A. Not necessarily more problems than the Iridium launch.
I find it odd that the NASA Launch Schedule page (also landings) has a listing for the Orbital ATK OA-7 mission but nothing on CRS-10.
NASA Glenn / Zin Technologies Zero Boil off Tank aka ZBOT experiment is finally supposed to be on this mission.
Is ZBOT launched full of cryogen?
Quote from: Comga on 01/18/2017 06:45 amIs ZBOT launched full of cryogen?Nope, attached is description of the experiment. Propellant depots thread may be a better place for discussion.
So far I have not found a direct statement that this is internal cargo, to be operated directly by the astronauts, not an external experiment as are other parts of STP-H5. Needing a vacuum jacket for insulation is a pretty strong clue that it will be inside the pressurized environment, as are the hints that it will be returned and reflown.
Operational Requirements and ProtocolsThe ZBOT test points are performed at three different fill levels: 70%, 80%, and 90%. The test tank is launched at a fill level of 70%. Particles are then injected into the fluid. The test fluid, P-n-P, is pre-conditioned to a nominal starting point temperature prior to each test. Tests fall into three categories: jet-mixing, subcooled jet mixing, and self-pressurization tests. Once tests are completed, the Fluid Reservoir are used to increase the fluid level in the test to the 80% and 90%. Dissolved gas are removed from the test fluid after each fill adjustment. Also, additional particles are injected to the fluid adjustment. There are a total of 52 test points, 23 each at the 70% and 90% fill levels, and 6 test points at the 80% fill level. Data are downlinked periodically. Return of the hardware is not required for data retrieval.On-orbit procedures cover the installation of the hardware into the Microgravity Science Glovebox (MSG). During installation the crew must evacuate air from hoses and fill the water loop. The hoses are evacuated using the Microgravity Science Glovebox vacuum exhaust system (MSG VES). The water loop is filled from the ZBOT Water Reservoir. After the hardware is installed, the crew inject particles into the Test Section between 3-5 times. Experimental runs are controlled from the ground.
The launch before SpX10 has been delayed by a week (from 23 Jan to 30 Jan) https://forum.nasaspaceflight.com/index.php?topic=40374.msg1632104#msg1632104 so launch now likely Feb 15 if there's a 1-for-1 delay. Does anyone know if it is likely to be an equal delay for the launch after Echostar 23 if its problems are due to pad readiness? What is the fastest they could turn around a pad? The HIF must be sufficient for simultaneously processing two missions, right? Or are there bottlenecks in equipment? Thanks
Very much still working this, but despite some good TEL testing at the pad over recent days (including a cool test relating to how the TEL will work differently than you've seen before at SLC-40), there's a lot of doubt about making Feb 3, or even close to that. This is literally like a brand new pad, there's bound to be teething issues and you really don't want something failing on your pad at T-0!Working is as it's not documented (where you see "X company requesting change to NET....") but what I'm being told. Could get interesting as CRS-10 is fast becoming a priority, with Dragon barging her shoulders in the line saying "I'm more important!" in a Jim-style "more than a ComSat launch" Again, working it, preliminary - but I always pass on launch date stuff out of L2/where ever as I know folk book flights/hotels. Don't change any plans, but have options to do so.
Quote from: Chris Bergin on 01/28/2017 01:33 pmVery much still working this, but despite some good TEL testing at the pad over recent days (including a cool test relating to how the TEL will work differently than you've seen before at SLC-40), there's a lot of doubt about making Feb 3, or even close to that. This is literally like a brand new pad, there's bound to be teething issues and you really don't want something failing on your pad at T-0!Working is as it's not documented (where you see "X company requesting change to NET....") but what I'm being told. Could get interesting as CRS-10 is fast becoming a priority, with Dragon barging her shoulders in the line saying "I'm more important!" in a Jim-style "more than a ComSat launch" Again, working it, preliminary - but I always pass on launch date stuff out of L2/where ever as I know folk book flights/hotels. Don't change any plans, but have options to do so.But didn't Jim say it's just tang and t-shirts?
If CRS-10 goes first, will it ride F9-31 or F9-32? - Ed Kyle