Lobo,
A couple of things:
You could not be more wrong on the cost per flight of STS. The average yearly budget for the entire program was 3 billion. You can't spend more than 300 percent of your yearly budget.
Also with respect to Orion was not designed by MSFC. It is not even a MSFC project. I think some of the LockMart people will take issue with your statement that NASA just handed them a completed and detailed design and said "build this for me underlings". There are many other things wrong with your statements that flow from this misunderstanding.
First, $1 billion per lauch is a number I've gotten from around these forums. I think the number includes the annual cost of running KSC in addition to the dedicated Shuttle budget. Perhaps that's where the number comes from. It's never quite simple to put a number on a launch, because the Shuttle is the only thing KSC launches, so it's expenses need to be factored in, as well as the actual costs of shuttle processing, ET, and SRB's, SRB retrieval, and other direct associated costs.
So I was saying maybe a high price tag on Orion factored in other overhead than just the direct costs of Orion, otherwise, $800 million would be a stupid-high price.
With respect to Orion, perhaps it wasn't specifically MSFC, that was my assumption of where at NASA it was designed. (Where else at NASA would it have been designed?)
LM's CEV design wasn't even a capsule, it was a space plane.
From Astronautix, not that they are the Bible, but they are usually pretty accurate:
http://www.astronautix.com/craft/cev.htm"When Mike Griffin was appointed NASA Administrator,
he threw out the previous elaborate plans for evolutionary development of a Crew Exploration Vehicle through a long, expensive, 'spiral' development process. Instead he obtained White House backing to plunge ahead using existing technology and NASA's best judgment.
The imaginative proposals from industry were largely ignored, except where they supported NASA's own conclusions. Lockheed and Northrop were notified that they had 'won' the CEV design competition in June 2005,
except that they would be only be allowed to make final bids based on the design dictated by NASA. NASA's own configuration was called 'Apollo on steroids'. "
"
NASA proposed a spacecraft with 23% less total mass than the Apollo CSM, 25 metric tons, but with a greater basic diameter of 5.5 m, rather than Apollo's 3.9 m. The re-entry vehicle was a 41% scaled up version of the Apollo command module. This would have over three times the internal volume and double the surface area of the Apollo capsule, but NASA claimed its mass could be limited to only 64% more than the Apollo design. Despite the increase in volume and mass, it would provide accommodation for only four to six crew (versus three to five in Apollo), plus up to 400 kg of payload that could be returned from orbit. An unmanned version of the capsule, with all crew provisions removed, could deliver or return up to 3500 kg of cargo to the International Space Station. "
"
By the end of 2005 it was clear that NASA was going to dictate the design of both the CEV and its shuttle-derived launch vehicle. It looked like the errors of the original Apollo program would be repeated. These included a decision process that proceeded from false assumptions; and not taking the minimum-mass approach. "
"This doesn't even touch on the matter on the innovative designs that were suggested in the first round of CEV proposals that NASA would not even comment on. The same approach was used in Apollo. First, proposals from industry were solicited. In both the Apollo and CEV cases these were imaginative, innovative, and incorporated all of the lessons of hundreds of millions of dollars of advanced research funded not just by NASA, but also by industry and the US Air Force. Superior contractor designs using the Soyuz-type separate orbital module or a winged spaceplane approach were made in both cases. In the case of the CEV, the team that designed and flew SpaceShipOne on the first civilian manned spaceflight offered to build a complete (four-crew) air-launched booster and spacecraft that would do the job for one-fortieth of the CEV/CLV cost!. In both the Apollo and CEV cases the contractors were thanked,
and NASA then proceeded with its own in-house government design. This was then suitably tweaked until it would passed the Congressional pork test. "
So...what other things did I get wrong that stemmed from my "misunderstanding"?
So how exactly to Orion get to look like it did when LockMart's CEV concept was a space plane, if NASA didn't dictate it to them?
Where, if not MSFC, did NASA make it's own in-house government design? (my assumption was it would have been done there)
Either you are right, or Astronautix is...I was just going with them. Don't shoot the messenger...