Hi Richo,
I fully agree with you, this will be the most viable solution.

And here is the next update, and so back to various detail work on the
SRB supports and their
Hold-down posts.
Because the
Aft skirt hold-down posts of the SRBs with 2 mm are very narrow,

I have carefully pre-drilled the holes for the bolts (0.5 mm) for the fixing of the stack with the gimlet first with 0.5 mm,


and drilled then for easier threading of the stack to 0.8 mm diameter.

And the Hold-down posts are constructed from these parts.

The cone tips get cores of a 3.3 mm rod with a 0.5 mm hole for the reception of the bolt pins (0.5 mm). The cone tips sit on a base plate (1.5 mm) and receive above as the
Aft skirt shoe a small plate from sheet 4x4x1 mm.

This is now such a pre-assembled body for the Hold-down post (left) and next to it an attempt for the side locking pin of the
Shoe retainer mechanism, which however still not convinced me.



Since this solution with the coated brass wire (blue) seems manufactured bit too time-consuming from processing, I further considered and once cut the rods.


Therefore here now another attempt made of plastic with a square profile (1 mm), with a glued rod (0,8 mm) as bolt.

This allows then but easier to produce and I like even better, as you can see on this picture.


And so I will also build now the remaining seven Hold-down posts.

And most recently the small Blast shields come then to the top of the rear Hold down posts.