#40
by
Chris Bergin
on 08 Jul, 2011 07:50
-
Freedom Star and Liberty Star are on station in the Atlantic.
-
#41
by
Chris Bergin
on 08 Jul, 2011 07:53
-
-
#42
by
Chris Bergin
on 08 Jul, 2011 08:01
-
Two hours into tanking, around 2/3rds through the process.
GUCP leak detectors will be sniffing for GH2.
-
#43
by
Chris Bergin
on 08 Jul, 2011 08:03
-
And one hour from the next BIH at T-3 hours.
-
#44
by
Chris Bergin
on 08 Jul, 2011 08:10
-
20 minutes to Crew Wake up.
-
#45
by
Chris Bergin
on 08 Jul, 2011 08:16
-
Closing in on LH2 topping now. Stack showing signs of all that prop.
Absolutely no issues in work.
-
#46
by
Chris Bergin
on 08 Jul, 2011 08:23
-
LH2 topping 15 minutes ahead of schedule. ET-138 must be thirsty today
-
#47
by
Chris Bergin
on 08 Jul, 2011 08:25
-
-
#48
by
Chris Bergin
on 08 Jul, 2011 08:36
-
The crew's alarm clocks will be buzzing.
Kathy Winters has provided another weather brief. Go conditions...... at the moment.
-
#49
by
Chris Bergin
on 08 Jul, 2011 08:38
-
-
#50
by
Chris Bergin
on 08 Jul, 2011 08:38
-
-
#51
by
Chris Bergin
on 08 Jul, 2011 08:38
-
-
#52
by
Chris Bergin
on 08 Jul, 2011 08:39
-
-
#53
by
Chris Bergin
on 08 Jul, 2011 08:43
-
Very nice shot of the aft..
-
#54
by
Chris Bergin
on 08 Jul, 2011 08:49
-
In the Firing Room:
ET-138 into LH2 Stable Replenish. LOX 10 minutes away.
-
#55
by
Chris Bergin
on 08 Jul, 2011 08:50
-
T-3 hours and holding (BIH) in around 10 minutes too.
-
#56
by
Chris Bergin
on 08 Jul, 2011 08:56
-
Really venting now.
-
#57
by
Chris Bergin
on 08 Jul, 2011 09:01
-
Tanking complete two minutes ahead of the top of the hour.
Now T-3 hours and HOLDING. BIH.
-
#58
by
Chris Bergin
on 08 Jul, 2011 09:02
-
Final Inspection Team (FIT) waiting for clearance to enter the pad.
-
#59
by
Chris Bergin
on 08 Jul, 2011 09:03
-
Nice.......