#140
by
Ronsmytheiii
on 21 May, 2010 12:14
-
6 turns on bolt H1, battery echo installed, Garrett posing Fonz style for the camera
-
#141
by
Chris Bergin
on 21 May, 2010 12:15
-
Garrett posing Fonz style for the camera
That was brilliant. Really want to see that in hi res!
-
#142
by
Ronsmytheiii
on 21 May, 2010 12:16
-
removing scoops, then will head to battery 6
-
#143
by
Ronsmytheiii
on 21 May, 2010 12:17
-
repositioning APFR/Big-G to battery 6 location
-
#144
by
Ronsmytheiii
on 21 May, 2010 12:19
-
Garrett installing scoops on battery 6, last battery to be changed out for the mission
-
#145
by
Ronsmytheiii
on 21 May, 2010 12:20
-
asking about island off the coast release H1 bolt first, released, off Spain and portugal
-
#146
by
Ronsmytheiii
on 21 May, 2010 12:22
-
working bolt H2 now, 16-17 turns expected, now unbolted
-
#147
by
Ronsmytheiii
on 21 May, 2010 12:24
-
-
#148
by
Ronsmytheiii
on 21 May, 2010 12:25
-
battery removed, back looks good, Garrett out of the APFR
-
#149
by
Ronsmytheiii
on 21 May, 2010 12:26
-
Loss of Ku, shuttle KU in 3 minutes and station in 15, crew Shepparding battery back to the ICC install position
-
#150
by
Ronsmytheiii
on 21 May, 2010 12:30
-
-
#151
by
Ronsmytheiii
on 21 May, 2010 12:32
-
Garrett will GCA arm in, FOD check on battery good
-
#152
by
Ronsmytheiii
on 21 May, 2010 12:33
-
-
#153
by
Ronsmytheiii
on 21 May, 2010 12:36
-
brakes on Garrett getting on the ICC to assist Mike in battery instillation
-
#154
by
Ronsmytheiii
on 21 May, 2010 12:39
-
battery 6 softdocked on the pallet, driving bolt H2 for 16-17 turns PGT settings Bravo 7 clockwise 2
-
#155
by
Ronsmytheiii
on 21 May, 2010 12:39
-
H2 driven, now H1 for 5-6 turns
H1 driven, will remove scoops and fold over MLI, battery 6 installed on the ICC-VLD
-
#156
by
Ronsmytheiii
on 21 May, 2010 12:44
-
Garrett getting into position on the ICC, Mike will GCA the arm into position to reach battery Foxtrot
No ku right now
-
#157
by
Ronsmytheiii
on 21 May, 2010 12:45
-
KU on station side returns, SSRMS moving in
-
#158
by
Ronsmytheiii
on 21 May, 2010 12:49
-
GCA complete, brakes on SSRMS, sun has set, Garret working MLI on Battery echo site
-
#159
by
Ronsmytheiii
on 21 May, 2010 12:51
-
scoops installed on battery foxtrot, time to unbolt H1, 6-7 turns
PGT: Bravo 7 counterclosckwise 2. After 6 turns it is released