Kyle reviewing the IFAs, really just the heater fail on the L3D RCS thruster and the He Reg. No mission impact.
-
#21
by
Chris Bergin
on 17 May, 2010 09:28
-
-
#22
by
Chris Bergin
on 17 May, 2010 09:30
-
PGT, good to use on ISS or HST
-
#23
by
Chris Bergin
on 17 May, 2010 09:47
-
-
#24
by
Chris Bergin
on 17 May, 2010 09:51
-
Setting up viewing from Atlantis, not a problem with reflection, but told if he wants to do "private stuff" to move out of the path of the reflection
-
#25
by
Chris Bergin
on 17 May, 2010 09:53
-
I reckon they are ahead of the timeline by a bit.
-
#26
by
Ronsmytheiii
on 17 May, 2010 10:10
-
-
#27
by
Chris Bergin
on 17 May, 2010 10:10
-
EMU fans being activated
-
#28
by
Chris Bergin
on 17 May, 2010 10:10
-
-
#29
by
Chris Bergin
on 17 May, 2010 10:13
-
-
#30
by
Ronsmytheiii
on 17 May, 2010 10:13
-
checking lights
-
#31
by
Chris Bergin
on 17 May, 2010 10:14
-
-
#32
by
Chris Bergin
on 17 May, 2010 10:16
-
-
#33
by
Ronsmytheiii
on 17 May, 2010 10:17
-
going to EMU purge, step 6 not required
-
#34
by
Chris Bergin
on 17 May, 2010 10:19
-
And that's 30 minutes ahead of schedule, so they are doing well.
-
#35
by
Ronsmytheiii
on 17 May, 2010 10:24
-
GO to repress the airlock
-
#36
by
Ronsmytheiii
on 17 May, 2010 10:27
-
moving the ICC-VLD to the EVA site
-
#37
by
Ronsmytheiii
on 17 May, 2010 10:38
-
steps 3 and 10 not required
-
#38
by
Ronsmytheiii
on 17 May, 2010 10:40
-
attaching Garret's mini work station, Steve-O's already attatched
-
#39
by
Ronsmytheiii
on 17 May, 2010 10:47
-
EVA-1 overview: