-
#480
by
oxford750
on 30 Aug, 2009 03:29
-
To Whom it may concern, this might be in the wrong section but I don't know where to put it.
I have seen the moon move across the sky over the course of 2-3 hours but why did the moon move so fast last night at the launch.
2. Are there photos of thrusters l4d,l2d,l3d,l5d,l5l
and the same ones on the right side . I have only seen l4l,l2l,l3l,l1l,l1a,l3a,l4u,l2u,l1u even from an SSME change photos.
Thanks
Oxford750
-
#481
by
Jorge
on 30 Aug, 2009 03:47
-
To Whom it may concern, this might be in the wrong section but I don't know where to put it.
I have seen the moon move across the sky over the course of 2-3 hours but why did the moon move so fast last night at the launch.
Narrow angle camera.
Plus, the moon's apparent motion is faster than many people realize. It moves its own diameter about every two minutes. This is not easily apparent when watching the moon at night, even with a single landmark in front of the moon, because most people have an unconscious tendency to move their heads to keep the landmark aligned with the moon. Aligning two landmarks with the moon provides a reference to keep the head steady. (Or set up binoculars on a fixed tripod, or use a telescope.)
-
#482
by
oxford750
on 30 Aug, 2009 06:18
-
To Whom it may concern, this might be in the wrong section but I don't know where to put it.
I have seen the moon move across the sky over the course of 2-3 hours but why did the moon move so fast last night at the launch.
Narrow angle camera.
Plus, the moon's apparent motion is faster than many people realize. It moves its own diameter about every two minutes. This is not easily apparent when watching the moon at night, even with a single landmark in front of the moon, because most people have an unconscious tendency to move their heads to keep the landmark aligned with the moon. Aligning two landmarks with the moon provides a reference to keep the head steady. (Or set up binoculars on a fixed tripod, or use a telescope.)
Thanks Jorge
Oxford750
-
#483
by
Chris Bergin
on 30 Aug, 2009 16:03
-
Here's a question that'll make Jim wince

When is an orbiter's birthday? I know PAO are going on the maiden launch date - and that's cool, we'll do likewise. However, I'd of thought it would have been maybe her first powerup at Palmdale or when the orbital first arrived at KSC on the back of the SCA?
How do the Navy work this? Commission date?
-
#484
by
Jim
on 30 Aug, 2009 16:48
-
Here's a question that'll make Jim wince 
When is an orbiter's birthday? I know PAO are going on the maiden launch date - and that's cool, we'll do likewise. However, I'd of thought it would have been maybe her first powerup at Palmdale or when the orbital first arrived at KSC on the back of the SCA?
How do the Navy work this? Commission date?
Or when the first piece is placed in the final assembly rig, equivalent to when a ship's keel is laid.
-
#485
by
psloss
on 30 Aug, 2009 16:55
-
When is an orbiter's birthday? I know PAO are going on the maiden launch date - and that's cool, we'll do likewise. However, I'd of thought it would have been maybe her first powerup at Palmdale or when the orbital first arrived at KSC on the back of the SCA?
As these things go, today is definitely a big silver anniversary, but I think what it's an anniversary of is a matter of preference. (Not a big deal one way or another.)
-
#486
by
ChrisGebhardt
on 30 Aug, 2009 18:11
-
Very true, Philip.
And here's a relatively complete list of her various birthdays/milestones:
January 29, 1979 Contract Award
August 27, 1979 Start long lead fabrication of Crew Module
June 20, 1980 Start fabrication lower fuselage
November 10, 1980 Start structural assembly of aft-fuselage
December 8, 1980 Start initial system installation aft fuselage
March 2, 1981 Start fabrication/assembly of payload bay doors
October 26, 1981 Start initial system installation, crew module, Downey
January 4, 1982 Start initial system installation upper forward fuselage
March 16, 1982 Midfuselage on dock, Palmdale
March 30, 1982 Elevons on dock, Palmdale
April 30, 1982 Wings arrive at Palmdale from Grumman
April 30, 1982 Lower forward fuselage on dock, Palmdale
July 16, 1982 Upper forward fuselage on dock, Palmdale
August 5, 1982 Vertical stabilizer on dock, Palmdale
September 3, 1982 Start of Final Assembly
October 15, 1982 Body flap on dock, Palmdale
January 11, 1983 Aft fuselage on dock, Palmdale
February 25, 1983 Complete final assembly and closeout installation, Palmdale
February 28, 1983 Start initial subsystems test, power-on, Palmdale
May 13, 1983 Complete initial subsystems testing
July 26, 1983 Complete subsystems testing
August 12, 1983 Completed Final Acceptance
October 16, 1983 Rollout from Palmdale
November 5, 1983 Overland transport from Palmdale to Edwards
November 9, 1983 Delivery to Kennedy Space Center
June 2, 1984 Flight Readiness Firing
August 30, 1984 First Flight (41-D)
-
#487
by
psloss
on 30 Aug, 2009 18:54
-
Very true, Philip.
And here's a relatively complete list of her various birthdays/milestones:
January 29, 1979 Contract Award
August 27, 1979 Start long lead fabrication of Crew Module
June 20, 1980 Start fabrication lower fuselage
November 10, 1980 Start structural assembly of aft-fuselage
December 8, 1980 Start initial system installation aft fuselage
March 2, 1981 Start fabrication/assembly of payload bay doors
October 26, 1981 Start initial system installation, crew module, Downey
January 4, 1982 Start initial system installation upper forward fuselage
March 16, 1982 Midfuselage on dock, Palmdale
March 30, 1982 Elevons on dock, Palmdale
April 30, 1982 Wings arrive at Palmdale from Grumman
April 30, 1982 Lower forward fuselage on dock, Palmdale
July 16, 1982 Upper forward fuselage on dock, Palmdale
August 5, 1982 Vertical stabilizer on dock, Palmdale
September 3, 1982 Start of Final Assembly
October 15, 1982 Body flap on dock, Palmdale
January 11, 1983 Aft fuselage on dock, Palmdale
February 25, 1983 Complete final assembly and closeout installation, Palmdale
February 28, 1983 Start initial subsystems test, power-on, Palmdale
May 13, 1983 Complete initial subsystems testing
July 26, 1983 Complete subsystems testing
August 12, 1983 Completed Final Acceptance
October 16, 1983 Rollout from Palmdale
November 5, 1983 Overland transport from Palmdale to Edwards
November 9, 1983 Delivery to Kennedy Space Center
June 2, 1984 Flight Readiness Firing
August 30, 1984 First Flight (41-D)
I grew up in the L.A. area, so the rollout ceremonies and delivery to Florida were a bigger deal there. All the orbiters got their picture in the papers when that happened.
-
#488
by
TJL
on 30 Aug, 2009 19:40
-
Was wondering why STS 131 is scheduled to carry 7 crew members where every other remaining mission carries 6?
Thank you.
-
#489
by
ChrisGebhardt
on 30 Aug, 2009 19:46
-
Was wondering why STS 131 is scheduled to carry 7 crew members where every other remaining mission carries 6?
Thank you.
Payload upmass requirements on the last missions require smaller crew sizes.
-
#490
by
TJL
on 30 Aug, 2009 19:58
-
Thanks, Chris, but wouldn't NASA want to maximize upmass on "131" as well?
-
#491
by
psloss
on 30 Aug, 2009 20:04
-
And here's a relatively complete list of her various birthdays/milestones:
January 29, 1979 Contract Award
August 27, 1979 Start long lead fabrication of Crew Module
June 20, 1980 Start fabrication lower fuselage
November 10, 1980 Start structural assembly of aft-fuselage
December 8, 1980 Start initial system installation aft fuselage
March 2, 1981 Start fabrication/assembly of payload bay doors
October 26, 1981 Start initial system installation, crew module, Downey
January 4, 1982 Start initial system installation upper forward fuselage
March 16, 1982 Midfuselage on dock, Palmdale
March 30, 1982 Elevons on dock, Palmdale
April 30, 1982 Wings arrive at Palmdale from Grumman
April 30, 1982 Lower forward fuselage on dock, Palmdale
July 16, 1982 Upper forward fuselage on dock, Palmdale
August 5, 1982 Vertical stabilizer on dock, Palmdale
September 3, 1982 Start of Final Assembly
October 15, 1982 Body flap on dock, Palmdale
January 11, 1983 Aft fuselage on dock, Palmdale
February 25, 1983 Complete final assembly and closeout installation, Palmdale
February 28, 1983 Start initial subsystems test, power-on, Palmdale
May 13, 1983 Complete initial subsystems testing
July 26, 1983 Complete subsystems testing
August 12, 1983 Completed Final Acceptance
October 16, 1983 Rollout from Palmdale
November 5, 1983 Overland transport from Palmdale to Edwards
November 9, 1983 Delivery to Kennedy Space Center
June 2, 1984 Flight Readiness Firing
August 30, 1984 First Flight (41-D)
Hope this is OK, but for grins a couple of screenshots from maybe five seconds of a local news report during STS-5; the rest I missed. Unfortunately, this was the only tape I owned at the time and I was more focused on the mission (it was EOM day at the time).
-
#492
by
ChrisGebhardt
on 30 Aug, 2009 20:26
-
Thanks, Chris, but wouldn't NASA want to maximize upmass on "131" as well?
There are three other mission after STS-131. As such, it's just not that much of a concern.
This might help explain it a little better.
http://www.nasaspaceflight.com/2009/02/sts-131-logistics-flight-baselined-by-prcb/The mission is already deep into planning and is a very complex logistics flight (which brings up a lot of supplies and upmass to begin with). The mission was baselined as a 12-day flight but because of everything that needs to take place on the mission they are extending it to 13-days to make sure the 7-member crew can complete all the objectives. Reducing crew size on that mission for the sake of upmass would not be a good move.
UPDATE: Also, STS-133 (the final flight) will only carry 5 crew members, not 6.
-
#493
by
TJL
on 30 Aug, 2009 20:37
-
Thank you, Chris...now it makes sense.
-
#494
by
Antares
on 31 Aug, 2009 01:04
-
Those are pretty cool stills, psloss. If it's not available elsewhere, you might think about putting the whole video on L2 Historical.
-
#495
by
Danny Dot
on 31 Aug, 2009 02:26
-
Does anyone know if there is a plan on the books in shuttle to do a planned prebank if needed for ascent performance? It gives about 800 pounds, IIRC, and Jon Harpold himself approved it.
I am thinking it might still be useful for some of the flights left. It wouldn't be surprised if some of them aren't bumping up on the max ascent performance to carry stuff to station. Even if it would allow us to carry more water up, that would be a plus.
Station needs to be stuffed full of supplies when shuttle is retired.
Danny Deger
-
#496
by
elmarko
on 31 Aug, 2009 09:45
-
Didn't we do this topic a few weeks ago? I was whining about how you'd cope with an underburn if you'd already targetted for a prebank or something like that.
-
#497
by
ChrisGebhardt
on 31 Aug, 2009 22:46
-
Sorry for the ignorance, but what's a prebank?
-
#498
by
GLS
on 31 Aug, 2009 23:29
-
Prebank is a maneuver you do so you "fall faster" into the atmosphere. It's done between the D/O burn and EI, and it's just banking the orbiter so that the lift goes to the side instead of upwards... thus the orbiter falls faster... and you want to do that if you have a "D/O underburn" or in an AOA.
-
#499
by
Lee Jay
on 31 Aug, 2009 23:36
-
Presumably that means you *plan* for a deorbit underburn thereby freeing up OMS propellant for use on ascent, thus giving you more ascent performance?