#380
by
Kel
on 16 May, 2009 18:57
-
MCC-H notes that they need to modify their aliveness test - didn't expect to be this far along
-
#381
by
Lee Jay
on 16 May, 2009 18:58
-
CAPCOM - "We didn't expect to be this far along".
-
#382
by
Chris Bergin
on 16 May, 2009 18:58
-
They are way, way ahead of the timeline. Only clean up activities, so EVA ending soon.
-
#383
by
Kel
on 16 May, 2009 18:59
-
Elapsed time 5:23.
Just clean up left.
-
#384
by
dotdk
on 16 May, 2009 19:00
-
Time to do get ahead? A NOBL or something?
-
#385
by
AnalogMan
on 16 May, 2009 19:01
-
Elapsed time 5:23.
Just clean up left.
I think they will also close the -V2 shroud doors after this cleanup, but that is only a 15 min timetabled task.
-
#386
by
psloss
on 16 May, 2009 19:01
-
Time to do get ahead? A NOBL or something? 
Once they've got the -V2 doors closed, I was wondering if they'd consider that...
-
#387
by
Kel
on 16 May, 2009 19:05
-
Time to do get ahead? A NOBL or something? 
Once they've got the -V2 doors closed, I was wondering if they'd consider that...
Doesn't sound like any extras today after closing the doors
-
#388
by
psloss
on 16 May, 2009 19:05
-
Time to do get ahead? A NOBL or something? 
Once they've got the -V2 doors closed, I was wondering if they'd consider that...
Looking again, one problem with the NOBLs is that they are on the other side of the telescope (+V2 instead of -V2). Not sure there's time to rotate the telescope around.
-
#389
by
AnalogMan
on 16 May, 2009 19:06
-
Time to do get ahead? A NOBL or something?
Once they've got the -V2 doors closed, I was wondering if they'd consider that...
Original timeline was to finish closing -V2 doors at 5:50 PET, we're at 5:30 now, so unless they extend the EVA they probably won't have time to do anything else.
-
#390
by
Retired Downrange
on 16 May, 2009 19:08
-
Good aliveness test on the COS
-
#391
by
Kel
on 16 May, 2009 19:08
-
Stowing tools before closing shroud doors
-
#392
by
Chris Bergin
on 16 May, 2009 19:09
-
-
#393
by
Kel
on 16 May, 2009 19:09
-
Good aliveness test on the COS
Functional test still to come
-
#394
by
Retired Downrange
on 16 May, 2009 19:11
-
Bravo Zulu to the team on this EVA
GREAT work and choreographing,
What a Team!
[edit] ...not to be obscure, ...Bravo Zulu is a naval signal, conveyed by flaghoist or voice radio, meaning "Well Done";
-
#395
by
GoForTLI
on 16 May, 2009 19:11
-
Time to do get ahead? A NOBL or something?
Once they've got the -V2 doors closed, I was wondering if they'd consider that...
Original timeline was to finish closing -V2 doors at 5:50 PET, we're at 5:30 now, so unless they extend the EVA they probably won't have time to do anything else.
PAO saying EVA should be completed at 6+40.
-
#396
by
Kel
on 16 May, 2009 19:14
-
-
#397
by
Kel
on 16 May, 2009 19:16
-
Drew setting up to get back into foot restraint in preparation for door closure
-
#398
by
Chris Bergin
on 16 May, 2009 19:18
-
-
#399
by
Kel
on 16 May, 2009 19:19
-
Will close right door first