#260
by
Chris Bergin
on 08 Aug, 2008 18:07
-
Engineers are having a few problems with a washer on the tank (ET-127) during SRB mate ops. Still under engineering evaluation and may delay Atlantis rollover, but they have some flexibility to the right of the timeline if there's a slight delay.
Will do a big processing update for the fleet tonight.
-
#261
by
Orbiter
on 08 Aug, 2008 18:26
-
Engineers are having a few problems with a washer on the tank (ET-127) during SRB mate ops. Still under engineering evaluation and may delay Atlantis rollover, but they have some flexibility to the right of the timeline if there's a slight delay.
Will do a big processing update for the fleet tonight.
Course, its Atlantis, Ever hear the quote for Columbia? 'Columbia would never launch but when it did it would give you the best mission.' On topic anyways, what kind of Washer?
-
#262
by
Ford Mustang
on 08 Aug, 2008 18:55
-
Engineers are having a few problems with a washer on the tank (ET-127) during SRB mate ops. Still under engineering evaluation and may delay Atlantis rollover, but they have some flexibility to the right of the timeline if there's a slight delay.
Will do a big processing update for the fleet tonight.
Course, its Atlantis, Ever hear the quote for Columbia? 'Columbia would never launch but when it did it would give you the best mission.' On topic anyways, what kind of Washer?
Has nothing to do with the orbiter, just the luck of the flow.
-
#263
by
Chris Bergin
on 10 Aug, 2008 05:09
-
-
#264
by
Justin Space
on 10 Aug, 2008 07:04
-
Really good article again!!
-
#265
by
Chris Bergin
on 10 Aug, 2008 16:28
-
Thanking you. Going to get busy with 125 soon, as they head into FRR season.
-
#266
by
Ronsmytheiii
on 11 Aug, 2008 14:14
-
SLIC and ORUC being repositioned:
-
#267
by
Chris Bergin
on 13 Aug, 2008 08:35
-
-
#268
by
Chris Bergin
on 14 Aug, 2008 15:26
-
Per L2, no change to the launch dates. Remain as perviously scheduled.
-
#269
by
Chris Bergin
on 14 Aug, 2008 15:42
-
-
#270
by
shuttlefan
on 15 Aug, 2008 13:34
-
Chris is rollover still targetted for Monday despite the landing gear door issue?
-
#271
by
DaveS
on 15 Aug, 2008 14:00
-
Chris is rollover still targetted for Monday despite the landing gear door issue?
Yes. CTS is scheduled for 0600 hours Monday.
-
#272
by
Chris Bergin
on 16 Aug, 2008 05:50
-
Another L2 based flow update, focusing on the ongoing issue with the Nose Landing Gear (reason for the article going on last thing at night as this was an evolving situation right through to end of shift (and continuing tomorrow).
You might think "wow Chris, you know a lot about the landing gear" - when I don't....I'm mainly paraphrasing a very helpful engineer that's been talking us through the processing documention relating to this on L2. He's the star
http://www.nasaspaceflight.com/content/?cid=5491Her nose gear still isn't raised, they hope tomorrow. If Sunday, they should be able to get her out of the barn on Monday. We'll be following closely.
-
#273
by
shuttlefan
on 17 Aug, 2008 13:24
-
Is rollover still set for 0800 Eastern Time, on Monday?
-
#274
by
TJL
on 17 Aug, 2008 15:23
-
What is the latest on the "noise" heard from ET 129 (STS 126) when it was being moved in the VAB last week?
Thank you.
-
#275
by
Chris Bergin
on 17 Aug, 2008 15:47
-
Is rollover still set for 0800 Eastern Time, on Monday?
Yep, but will update in the morning.
What is the latest on the "noise" heard from ET 129 (STS 126) when it was being moved in the VAB last week?
Thank you.
You've read it

The most we have is via the morning reports on L2 (which I've also reported in the news articles) and the paper chase at MAF. The latest two or three articles note the plan of action and where they've got to with it. Monday will be interesting to see progress via the next reports on L2 (which I'll report as a news article).
Might be best to keep the ET-129 stuff on Endeavour's section.
-
#276
by
dsmillman
on 17 Aug, 2008 18:37
-
Can anyone provide more details on the delay in the rollover of Atlantis to the VAB because of tropical storm Fay?
-
#277
by
Chris Bergin
on 17 Aug, 2008 19:07
-
-
#278
by
Chris Bergin
on 17 Aug, 2008 19:20
-
NASA PAO note is a phone message.
USA:
No impact to launch schedule. 11 contingency days before payload to pad.
-
#279
by
Chris Bergin
on 18 Aug, 2008 14:40
-
Rollover is NET Tuesday, but more likely Thursday. Writing a processing report based on Monday's L2 processing reports.