#140
by
Chris Bergin
on 04 Jul, 2008 13:52
-
-
#141
by
shuttlepilot
on 04 Jul, 2008 20:25
-
It's good for me that they won't launch earlier, because I have already booked plane tickets and accomodation, and I was a bit scared about this.
-
#142
by
Chris Bergin
on 09 Jul, 2008 20:09
-
ET-127 is about to be completed. Hours to go and will be shipped in the morning (placed on to the barge). Non-L2 users won't know the amount of effort that's gone into this tank over the last few days, so will do an article.
-
#143
by
Orbiter
on 10 Jul, 2008 16:43
-
ET-127 is about to be completed. Hours to go and will be shipped in the morning (placed on to the barge). Non-L2 users won't know the amount of effort that's gone into this tank over the last few days, so will do an article.
I am assuming it was shipped by now?
-
#144
by
DaveS
on 10 Jul, 2008 17:11
-
ET-127 is about to be completed. Hours to go and will be shipped in the morning (placed on to the barge). Non-L2 users won't know the amount of effort that's gone into this tank over the last few days, so will do an article.
I am assuming it was shipped by now?
Nope. Roll-on-barge according to this morning's NTD report is 1800 local.
-
#145
by
Orbiter
on 10 Jul, 2008 17:27
-
ET-127 is about to be completed. Hours to go and will be shipped in the morning (placed on to the barge). Non-L2 users won't know the amount of effort that's gone into this tank over the last few days, so will do an article.
I am assuming it was shipped by now?
Nope. Roll-on-barge according to this morning's NTD report is 1800 local.
Thanks,
-
#146
by
Chris Bergin
on 10 Jul, 2008 17:53
-
-
#147
by
DaveS
on 10 Jul, 2008 19:56
-
-
#148
by
Chris Bergin
on 13 Jul, 2008 04:01
-
-
#149
by
Orbiter
on 13 Jul, 2008 04:18
-
-
#150
by
ChrisGebhardt
on 13 Jul, 2008 04:39
-
Excellent. I'd read about this but forgotten that it was debuting with this mission. Wonderful overview of where things stand now.
-
#151
by
Chris Bergin
on 13 Jul, 2008 09:17
-
Thanks, as I was going blind with that presentation
-
#152
by
cb6785
on 13 Jul, 2008 09:27
-
Interesting thing: It's the first time I see someone mention a possible STS-134 in a status report...
Chris, if the ET arrives at KSC on the 16th, do you now when the official mating date with the SRBs will be?
-
#153
by
Chris Bergin
on 13 Jul, 2008 09:43
-
Interesting thing: It's the first time I see someone mention a possible STS-134 in a status report...
Chris, if the ET arrives at KSC on the 16th, do you now when the official mating date with the SRBs will be?
Well spotted on the STS-134

We thought it was a typo on the L2 presentation, but we don't know. Wasn't going to change the content of the presentation in the article, so placed a "to be decided" type note with it.
ET/SRB Mate review has to take place first, and that's not till next week. Looking at next weekend at the earliest, as we believe some additional work is required on the tank in the checkout cell - might be done after mate, we'll see.
It'll be on L2 processing info next week, so when we know it'll be the first word on a set date.
-
#154
by
psloss
on 13 Jul, 2008 10:56
-
Well spotted on the STS-134
We thought it was a typo on the L2 presentation, but we don't know. Wasn't going to change the content of the presentation in the article, so placed a "to be decided" type note with it.
It would seem to be in-line with Mr. Shannon's recent comments to Bill Harwood.
-
#155
by
ChrisGebhardt
on 14 Jul, 2008 04:14
-
Thanks, as I was going blind with that presentation 
Hmm... I think I know what you mean there.
-
#156
by
Orbiter
on 14 Jul, 2008 18:14
-
I wonder when Rollover is for Atlantis.
-
#157
by
Ford Mustang
on 14 Jul, 2008 18:32
-
I wonder when Rollover is for Atlantis.
Most likely 7 or 8 days prior to rollout. Normally a week in the VAB before rollout.
-
#158
by
NASAAN101
on 15 Jul, 2008 01:37
-
she's spent almost a week in the VAB right, what are they doing during that time as far as the testing going to thr obiter?? NIKKI
-
#159
by
ChrisGebhardt
on 15 Jul, 2008 02:40
-
she's spent almost a week in the VAB right, what are they doing during that time as far as the testing going to thr obiter??
NIKKI
Mating ops, powered up integrated stack interface testing, and preps for rollout take place during the week in the VAB.