#1300
by
input~2
on 12 Aug, 2016 17:48
-
A little be confused. When did reference to GSLV-D9 appear? Notice the change in the schedule, but not sure why?
Annual Reports and Outcome Budgets for ISRO refer to a GSLV-F08.
Reference to GSLV D9 appeared in April 2015, may have to be checked again
-
#1301
by
russianhalo117
on 12 Aug, 2016 18:50
-
A little be confused. When did reference to GSLV-D9 appear? Notice the change in the schedule, but not sure why?
Annual Reports and Outcome Budgets for ISRO refer to a GSLV-F08.
Reference to GSLV D9 appeared in April 2015, may have to be checked again
Next Suborbital flight test target date is to be announced to public soon.
-
#1302
by
input~2
on 18 Aug, 2016 19:26
-
4 "missions" planned until the end of this year according to Shar director: ATV, GSLV-F05, PSLV-C35 and GSLV MkIII D1
youtu.be/ny3lw1TE9kw
-
#1303
by
input~2
on 18 Aug, 2016 19:57
-
2016 performed launches
1) January 20, 04:01UTC- PSLV(XL) C31 - IRNSS-1E
2) March 10, 10:31 UTC- PSLV(XL) C32 - IRNSS-1F
3) April 28, 07:20 UTC - PSLV (XL)C33 - IRNSS-1G
May 23, 01:30 UTC, RLV-TD HEX-01 (suborbital)
4) June 22, 03:55 UTC PSLV(XL) C34 - Cartosat-2C + GHGSat-D + BIROS +Swayam
+ SathyaBamaSat + Skysat-C1 + Dove (3x4)+ Lapan-A3 + M3MSat
August 28 00:30 UTC ATV-D02 -SPEX (suborbital)
5) September 8 11:20 UTC - GSLV MkII F05 (SLP)- INSAT-3DR
Tentative launch schedule
2016
August end 28 ~00:35 UTC- ATV-D02 - SPEX (suborbital)
NET September 8 10 11:22 UTC - GSLV MkII F05 (SLP)- INSAT-3DR
September 26 October - PSLV C35 (FLP) - SCATSat-1 + (Blacksky) Pathfinder-1 + PiSAT + Alsat-2B + Pratham + Alsat-1N + 2 foreign satellites (CanX-7?, Alsat-1B?)
December - GSLV Mk III D1 - GSAT-19
piggybacked on PSLV: CanX-7, Alsat-1B, Niusat
October 4, Ariane 5 - GSAT-18
2017
Q1 - PSLV C36 - Resourcesat-2A + IITMSAT + Max Valier + Venta-1
H1 - PSLV C37 - EMISAT/SPADEX
H1 end March - GSLV Mk II F09 - GSAT-9 (aka South Asia Sat)
April - PSLV C38 - Cartosat-2D
- GSLV Mk II F10 - GISAT (GEO Imaging SATellite)
- GSLV Mk II F11 - GSAT-6A
- PSLV - 8 Skysat-C (tbc)
December - PSLV - Cartosat-2E
- tbd- Mars Observation Mission
piggybacked on PSLV: Microsat, PlanetiQ-1, PlanetiQ-2, InnoSat-2 (Malaysia), CE-SAT1 (Japan), "3 Diamonds"
Q1- Ariane 5 - GSAT-11
Q1- Ariane 5 - GSAT-17
2018
- GSLV Mk II D9 - Chandrayaan-2
March - PSLV - Cartosat-3
July - PSLV - Oceansat-3
Q3 - PSLV - EnMap (Germany)
- GSLV Mk II F12 - GSAT-7A
(or December 2017) - GSLV Mk III D2 - GSAT-20
piggybacked on PSLV : IMS(Indian Mini Satellite)/Atmos, IMS-1E, IMS-1F, IinuSat, IMS-B, PARIKSHIT, NEMO-AM (FY 2018-19)
2019
March - PSLV - Cartosat-3A
Q2 - PSLV - RISAT-1A
- PSLV XL - Aditiya-1
December or 2020 - PSLV - Oceansat-3A
piggybacked on PSLV: HYSIS
2020
March - PSLV - Cartosat-3B
- PSLV - RISAT-2A
Q2 - PSLV - Resourcesat-3S
Q2 - PSLV - Resourcesat-3
2021
Q2 - PSLV - Resourcesat-3SA
Q2 - PSLV - Resourcesat-3A
- GSLV MkII - NISAR (NASA-ISRO SAR sat)
2022
Q1 - PSLV - Resourcesat-3B
updated August 23
updated August 25
updated August 28
updated September 8
-
#1304
by
input~2
on 24 Aug, 2016 09:01
-
-
#1305
by
input~2
on 25 Aug, 2016 09:24
-
-
#1306
by
isro-watch
on 10 Sep, 2016 20:41
-
During the post-launch talk by top ISRO officials. SDSC SHAR director talked of "double-digit" missions. Considering they have completed 7, in order to make it double digit , there are atleast 3 more missions
I am not sure but this may mean ,
PSLV-SCATSAT mission - Sep-end/Oct-begin
PSLV-RESOURCESAT-2A mission - End-Nov
LVM3-D1 mission - Dec
But, it can also mean ,
PSLV-SCATSAT mission - Sep-end/Oct-begin
GSAT-18/Ariane
LVM3-D1 mission - Dec
-
#1307
by
isro-watch
on 10 Sep, 2016 23:30
-
This video in Tamil by Dr.Sivan talks of the following launches:
Sep-26th - PSLV-Scatsat mission with commercial and student satellites.
It is followed by another PSLV mission
LVM3 - Dec-end
GSLV-F?? - South Asia Satellite
Chandrayaan-2 work progressing
-
#1308
by
K210
on 11 Sep, 2016 05:27
-
SouthAsiaSat and GSAT-9 are seperate missions not the same. SouthAsiaSat is currently set for march 2017 launch while gsat-9 will be launched sometime in 2018.
-
#1309
by
isro-watch
on 11 Sep, 2016 22:11
-
The first of the two Planeti-Q satellites may be on the Resourcesat-2A mission. Planeti-Q website gives a time frame of fall2016 to January 2017.
-
#1310
by
input~2
on 12 Sep, 2016 16:49
-
SouthAsiaSat and GSAT-9 are seperate missions not the same. SouthAsiaSat is currently set for march 2017 launch while gsat-9 will be launched sometime in 2018.
Do you have a source please?
-
#1311
by
input~2
on 12 Sep, 2016 17:30
-
2016 performed launches
1) January 20, 04:01UTC- PSLV(XL) C31 - IRNSS-1E
2) March 10, 10:31 UTC- PSLV(XL) C32 - IRNSS-1F
3) April 28, 07:20 UTC - PSLV (XL)C33 - IRNSS-1G
May 23, 01:30 UTC, RLV-TD HEX-01 (suborbital)
4) June 22, 03:565 UTC PSLV(XL) C34 - Cartosat-2C + GHGSat-D + BIROS +Swayam
+ SathyaBamaSat + Skysat-C1 + Dove (3x4)+ Lapan-A3 + M3MSat
August 28 00:30 UTC ATV-D02 -SPEX (suborbital)
5) September 8 11:20 UTC - GSLV MkII F05 (SLP)- INSAT-3DR
6) September 26 03:42UTC - PSLV (G3) C35 (FLP) - SCATSat-1 + (Blacksky) Pathfinder-1 + PiSAT + Alsat-2B + Pratham + Alsat-1N + CanX-7 + Alsat-1B
Tentative launch schedule
2016
December (or early 2017) - GSLV Mk III D1 - GSAT-19
October 4, Ariane 5 - GSAT-18
2017
Q1 (or November 2016) - PSLV C36 - Resourcesat-2A + IITMSAT + Max Valier + Venta-1
H1 - PSLV C37 - EMISAT/SPADEX
end March - GSLV Mk II F09 - GSAT-9 (aka South Asia Sat?)
April - PSLV C38 - Cartosat-2D
- GSLV Mk II F10 - GISAT (GEO Imaging SATellite)
- GSLV Mk II F11 - GSAT-6A
- PSLV - 8 Skysat-C (tbc)
December - PSLV - Cartosat-2E
- tbd- Mars Observation Mission
piggybacked on PSLV: Microsat, PlanetiQ-1, PlanetiQ-2, InnoSat-2 (Malaysia), CE-SAT1 (Japan), "3 Diamonds", Niusat
Q1- Ariane 5 - GSAT-11
Q1- Ariane 5 - GSAT-17
2018
- GSLV Mk II D9 - Chandrayaan-2
March - PSLV - Cartosat-3
July - PSLV - Oceansat-3
Q3 - PSLV - EnMap (Germany)
- GSLV Mk II F12 - GSAT-7A
(or December 2017) - GSLV Mk III D2 - GSAT-20
piggybacked on PSLV : IMS(Indian Mini Satellite)/Atmos, IMS-1E, IMS-1F, IinuSat, IMS-B, PARIKSHIT, NEMO-AM (FY 2018-19)
2019
March - PSLV - Cartosat-3A
Q2 - PSLV - RISAT-1A
- PSLV XL - Aditiya-1
December or 2020 - PSLV - Oceansat-3A
piggybacked on PSLV: HYSIS
2020
March - PSLV - Cartosat-3B
- PSLV - RISAT-2A
Q2 - PSLV - Resourcesat-3S
Q2 - PSLV - Resourcesat-3
2021
Q2 - PSLV - Resourcesat-3SA
Q2 - PSLV - Resourcesat-3A
- GSLV MkII - NISAR (NASA-ISRO SAR sat)
2022
Q1 - PSLV - Resourcesat-3B
updated Sept 15
updated Sept 21
updated Sept 24
updated Sept 26
updated Sept 28
-
#1312
by
input~2
on 13 Sep, 2016 04:21
-
SouthAsiaSat and GSAT-9 are seperate missions not the same. SouthAsiaSat is currently set for march 2017 launch while gsat-9 will be launched sometime in 2018.
What do you make of the
very low budget allocated to "SouthAsiaSat" in the last 3 years?
-
#1313
by
K210
on 13 Sep, 2016 06:25
-
SouthAsiaSat and GSAT-9 are seperate missions not the same. SouthAsiaSat is currently set for march 2017 launch while gsat-9 will be launched sometime in 2018.
What do you make of the very low budget allocated to "SouthAsiaSat" in the last 3 years?
In the post PSLV C-23 launch speeches PM narendra modi requested ISRO to develop a satelite for SAARC nations. Apart from that not much is known about SouthAsiaSat except that it is a approved program. GSAT-9 is actually supposed to be a replacement for INSAT-4CR which is why i suggest that southAsiaSat and GSAT-9 are seperate missions. However i could be wrong time will tell i guess.
-
#1314
by
vineethgk
on 14 Sep, 2016 04:46
-
GSAT-11 to be launched in early 2017GSAT-11, India’s advanced and heaviest communication spacecraft to date at 5,700 kg, is to be launched early next year on the European Ariane launch vehicle
M. Annadurai, Director of ISRO Satellite Centre or ISAC, Bengaluru, said, “The satellite is getting integrated [at ISAC.]. We are targeting the first quarter of 2017 for its launch.” This would be the first spacecraft to be integrated on ISRO’s new i-6k platform, he told The Hindu.
-
#1315
by
Alter Sachse
on 23 Sep, 2016 22:55
-
-
#1316
by
isro-watch
on 26 Sep, 2016 23:09
-
-
#1317
by
cbing92
on 27 Sep, 2016 07:21
-
-
#1318
by
vineethgk
on 27 Sep, 2016 13:21
-
http://www.thehindu.com/news/national/pslv-launches-eight-satellites/article9150837.ece
As stated in this article, the next launch will be Resourcesat-2A in November-2016
But in his speech, the chairman said about the assembly of LVM3, but didn't mention about the next PSLV or the Resourcesat. Can ISRO move up the schedule to launch another PSLV this year?
The SLP is blocked for the LVM3 launch till the end of the year. But it might be possible for them to get the FLP back up in a couple of months for another PSLV launch.
-
#1319
by
cbing92
on 27 Sep, 2016 15:25
-
http://www.thehindu.com/news/national/pslv-launches-eight-satellites/article9150837.ece
As stated in this article, the next launch will be Resourcesat-2A in November-2016
But in his speech, the chairman said about the assembly of LVM3, but didn't mention about the next PSLV or the Resourcesat. Can ISRO move up the schedule to launch another PSLV this year?
The SLP is blocked for the LVM3 launch till the end of the year. But it might be possible for them to get the FLP back up in a couple of months for another PSLV launch.
If the LVM3 mission schedule were to slip, it may be better to use the pad and resources to launch the Resourcesat. ISRO flew 6 missions in first 9 months, and the next one may take at least a gap of 3 months, if both LVM3 and Resourcesat were to fall out of schedule because of one another.