#1160
by
input~2
on 31 Aug, 2015 15:58
-
"We are also planning to launch three IRNSS satellites by December 2015, February 2016 and March 2016," he said.
So IRNSS 1E is there still.
You won't have PSLV-C29 and -C31 launched in the same month
-
#1161
by
isro-watch
on 01 Sep, 2015 03:44
-
PSLV C30 is getting ready for Astrosat launch in September on First Launch Pad (FLP)
Second Launch Pad (SLP) is vacant and I suppose they will start stacking for PSLV C29 TeLeos-1 mission ! They still have 3 months before the end of year for IRNSS-1E mission from FLP !
This is considering that the launch pads are not occupied by RLV-TD. I am not hopeful about any mission this year.
-
#1162
by
Ohsin
on 01 Sep, 2015 08:39
-
GSLV-F05, is targeted for launch in July 2016 and will carry the 2200 kg INSAT-3DR meteorological satellite. GSLV-F09 is planned in May 2017 to launch the GSAT-9 satellite
http://www.isro.gov.in/gslv-saga
-
#1163
by
spaceAsh
on 06 Sep, 2015 17:41
-
GSLV Mk-III version in December 2016.
Do we know anything about the payload of the MK-III mission in Dec 2016?
-
#1164
by
abhishek
on 06 Sep, 2015 18:29
-
GSLV Mk-III version in December 2016.
Do we know anything about the payload of the MK-III mission in Dec 2016?
GSAT 19E
-
#1165
by
chota
on 16 Sep, 2015 16:32
-
-
#1166
by
input~2
on 28 Sep, 2015 08:32
-
2015 performed Launches
March 28 11:49 UTC - PSLV(XL) C27 - IRNSS-1D
July 10 16:28 UTC - PSLV(XL) C28 FLP - 3 DMC3 + DeorbitSail-1 + CBNT-1
August 27 11:22 UTC - GSLV-D6 Mk II - GSAT-6 (military use)
September 28 04:30 UTC - PSLV (XL) C30 SLP- AstroSat-1 + LAPAN-A2 (Indonesia) +NLS-14/Ev9 (Canada) + 4 x Lemur (UK)
Tentative launch schedule
2015
December or 2016 PSLV(CA) C29 - TeLEOS-1 + KR 1 + VELOX C1 + 3 piggybacks (Singapore)
NET November end December - RLV-TD HEX-01 (suborbital)
Nov 10 - Ariane 5 - GSAT-15
2016
Feb or Dec 2015- PSLV(XL) C31 - IRNSS-1E
March - PSLV(XL) C32 - IRNSS-1F
- PSLV (XL) - IRNSS-1G
July - GSLV MkII F05- INSAT-3DR
September - PSLV C33 - Cartosat-2C + SRE-2
NET Q4 -GSLV MkII- SAARC sat
December - PSLV C35 - Resourcesat-2A
- RLV-TD HEX-01 (suborbital)
piggybacked on PSLV : M3MSat (Canada), Nemo-AM, 9 nano/micro US sats (Q1)
15 PSLV flights (C36 to C50) to be completed during the period 2017-2020
Jan 2017 to March 2018
2017 or end 2016 - PSLV - Scatsat-1
- PSLV - Cartosat-2D
May - GSLV Mk II F09 - GSAT-9
- GSLV Mk II F10 - GISAT (GEO Imaging SATellite)
- GSLV Mk II F11 - GSAT-6A
- PSLV - Oceansat-3
- PSLV - Cartosat-2E
- GSLV -Mk III D1 - GSAT-19
- tbd- Mars Observation Mission
- GSLV Mk II D9 - Chandrayaan-2
- foreign launcher - GSAT-17
- foreign launcher - GSAT-18
- foreign launcher - GSAT-11
piggybacked on PSLV : IITMSAT;STUDSAT-2, LAPAN A3
IMS(Indian Mini Satellite)/Atmos, IMS-1E, IMS-1F, Alsat-2B, IinuSat, IMS-B
April 2018-2019
- GSLV Mk II F12 - GSAT-7A
- GSLV Mk III D2 - GSAT-20
- PSLV - Cartosat-3
- PSLV - RISAT-1A
- PSLV XL - Aditiya-1
2018-Q3 - PSLV - EnMap (Germany)
2020
September - GSLV MkII - NI-SAR (NASA-ISRO SAR sat)
- PSLV C44
- PSLV C45
- PSLV C46
- PSLV C47
- PSLV C48
- PSLV C49
- PSLV C50
after 2020
- GSLV Mk III - Manned mission
updated on October 2
updated on October 13
-
#1167
by
isro-watch
on 29 Sep, 2015 01:46
-
There seems to be a commercial launch in Q1-2016. I suspect it is M3MSAT along with a few more US satellites
-
#1168
by
isro-watch
on 29 Sep, 2015 03:43
-
-
#1169
by
Ohsin
on 29 Sep, 2015 06:56
-
There seems to be a commercial launch in Q1-2016. I suspect it is M3MSAT along with a few more US satellites
On that article it says 5 US satellites would go up before 2016 ??
-
#1170
by
isro-watch
on 03 Oct, 2015 01:18
-
There seems to be a commercial launch in Q1-2016. I suspect it is M3MSAT along with a few more US satellites
On that article it says 5 US satellites would go up before 2016 ??
I assume they meant "before the end of 2016"
-
#1171
by
tappa
on 12 Oct, 2015 04:54
-
The IRNSS launch in December had to be added to the launch schedule.
-
#1172
by
input~2
on 12 Oct, 2015 15:22
-
The IRNSS launch in December had to be added to the launch schedule.
What about Teleos launch in December?
-
#1173
by
isro-watch
on 12 Oct, 2015 16:21
-
-
#1174
by
input~2
on 12 Oct, 2015 17:05
-
Peter B. de Selding @pbdes 46 minutes ago
Germany's DLR: EnMap hyperspectral mission, after multiple delays, now stabilized and moving to mid-2018 launch.#IAC2015
-
#1175
by
chota
on 12 Oct, 2015 22:39
-
-
#1176
by
zubenelgenubi
on 14 Oct, 2015 01:02
-
Are the next few PSLV launches (TeLEOS, IRNSS-1E, IRNSS-1F) all launching from the FLP, or will any of these use the SLP?
-
#1177
by
Ohsin
on 14 Oct, 2015 04:31
-
Are the next few PSLV launches (TeLEOS, IRNSS-1E, IRNSS-1F) all launching from the FLP, or will any of these use the SLP?
Integration usually takes 3-4 months(33 days for GSLV D6 was an exception not norm) but pad turnaround is just about a week and half. So I guess they need to use both pads.
-
#1178
by
s^3
on 14 Oct, 2015 20:54
-
-
#1179
by
Ohsin
on 17 Oct, 2015 02:42
-