#580
by
Ford Mustang
on 12 Jan, 2008 21:19
-
Looks like the camera got moved to a better position... And more work.
-
#581
by
ChrisC
on 12 Jan, 2008 21:33
-
I don't know where I saw it, but in one of these threads someone posted something to the effect that yesterday's ISS reboost for Progress phasing was going to force the STS-122/1E mission to rendezvous on flight day 4. That's not true. Here's what today's ISS status report says:
"Reboost Update: The ISS reboost yesterday by the twin SM main engines was successfully conducted on time (7:42pm EST). Purpose of the 1m 58s long maneuver burn was to establish the correct phasing conditions for 27S launch and the STS-122/1E launch season (FD3 rendezvous)."
http://www.hq.nasa.gov/osf/iss_reports/index.htm
-
#582
by
Cosmos27
on 13 Jan, 2008 01:00
-
ChrisC - 12/1/2008 5:33 PM
I don't know where I saw it, but in one of these threads someone posted something to the effect that yesterday's ISS reboost for Progress phasing was going to force the STS-122/1E mission to rendezvous on flight day 4. That's not true. Here's what today's ISS status report says:
"Reboost Update: The ISS reboost yesterday by the twin SM main engines was successfully conducted on time (7:42pm EST). Purpose of the 1m 58s long maneuver burn was to establish the correct phasing conditions for 27S launch and the STS-122/1E launch season (FD3 rendezvous)."
http://www.hq.nasa.gov/osf/iss_reports/index.htm
Thanks Chris C for clearing that incorrect info up! I thought I heard that info as well and I am so glad the ISS reboost has no ill effect on the STS 122 mission!
-
#583
by
Chris Bergin
on 13 Jan, 2008 04:43
-
And they're back for more...
-
#584
by
Chris Bergin
on 13 Jan, 2008 04:44
-
-
#585
by
Chris Bergin
on 13 Jan, 2008 05:44
-
Told the new connector is in the tank now. Happy engineer on the second image
-
#586
by
Chris Bergin
on 13 Jan, 2008 05:58
-
Wish we had audio :laugh: Looks like they're having a meeting.
As per L2: "LH2 tank vent scheduled for 3rd shift Sunday no earlier than 03:00."
-
#587
by
Chris Bergin
on 13 Jan, 2008 07:50
-
-
#588
by
Wisi
on 13 Jan, 2008 08:51
-
-
#589
by
Chris Bergin
on 13 Jan, 2008 15:07
-
Thanks

For those wondering why this installation took the best part of the weekend, they had wire splicing issues on Saturday morning.
Tank vent was delayed to 10am. One of the helmetball fans too....(I assume whatever team that is will suggest if he's a KSC or MAF guy)
-
#590
by
Jorge
on 13 Jan, 2008 15:37
-
Chris Bergin - 13/1/2008 10:07 AM
Thanks 
For those wondering why this installation took the best part of the weekend, they had wire splicing issues on Saturday morning.
Tank vent was delayed to 10am. One of the helmetball fans too....(I assume whatever team that is will suggest if he's a KSC or MAF guy) 
Most likely a MAF guy... Louisiana State University is west of New Orleans, in Baton Rouge. And they won the national championship in the Louisiana Superdome. But you can't tell for sure, because LSU has alumni at multiple centers.
-
#591
by
Chris Bergin
on 13 Jan, 2008 16:02
-
Ah, College Football. Thanks Jorge.
Can't confirm, but going off the webcam, there's not been any activity in shot, so we might be able to assume they are into the venting stage/leak checks.
-
#592
by
Jackson
on 13 Jan, 2008 17:26
-
http://www.nasaspaceflight.com/content/?cid=5330"STS-122 ECO related news content: *Scrub 1* - *MMT Debate* - *Scrub 2* - *Hale Memo* - *Forward Plan* - *Culprit Found* - *Tanking Test* - *Repair Options* - *MAF Plan* - *PRCB Debate* - *Plan Approved* - *Repair Schedule* - *Launch Date* - *New Issue* - *Hale Rallying Call* - *PRCB Launch Dates*"
So the latest is the 17th article you've written on the ECO sensor problems for STS-122
-
#593
by
Chris Bergin
on 13 Jan, 2008 17:36
-
Jackson - 13/1/2008 6:26 PM
http://www.nasaspaceflight.com/content/?cid=5330
"STS-122 ECO related news content: *Scrub 1* - *MMT Debate* - *Scrub 2* - *Hale Memo* - *Forward Plan* - *Culprit Found* - *Tanking Test* - *Repair Options* - *MAF Plan* - *PRCB Debate* - *Plan Approved* - *Repair Schedule* - *Launch Date* - *New Issue* - *Hale Rallying Call* - *PRCB Launch Dates*"
So the latest is the 17th article you've written on the ECO sensor problems for STS-122 
Well I wrote 16 of them, but I've got 21 to beat (ET-124's repairs after hail damage)
-
#594
by
Chris Bergin
on 13 Jan, 2008 20:44
-
New angle I believe, and if I'm not mistaken, you can see the plug on the installed external connector in the middle of the image:
-
#595
by
Ford Mustang
on 13 Jan, 2008 22:31
-
Looks like they've closed off the connector, I'm not sure if it's permanent or not (looks temporary..):
-
#596
by
Chris Bergin
on 13 Jan, 2008 22:53
-
Ford Mustang - 13/1/2008 11:31 PM
Looks like they've closed off the connector, I'm not sure if it's permanent or not (looks temporary..):
They have leak and electrical tests on the schedule before they spray the foam back on.
-
#597
by
on 14 Jan, 2008 02:00
-
-
#598
by
on 14 Jan, 2008 02:06
-
Images of the wires being spliced now on the media gallery
-
#599
by
ChrisGebhardt
on 14 Jan, 2008 04:22
-
Chris Bergin - 13/1/2008 1:36 PM
Jackson - 13/1/2008 6:26 PM
http://www.nasaspaceflight.com/content/?cid=5330
"STS-122 ECO related news content: *Scrub 1* - *MMT Debate* - *Scrub 2* - *Hale Memo* - *Forward Plan* - *Culprit Found* - *Tanking Test* - *Repair Options* - *MAF Plan* - *PRCB Debate* - *Plan Approved* - *Repair Schedule* - *Launch Date* - *New Issue* - *Hale Rallying Call* - *PRCB Launch Dates*"
So the latest is the 17th article you've written on the ECO sensor problems for STS-122 
Well I wrote 16 of them, but I've got 21 to beat (ET-124's repairs after hail damage) 
Patients my friend. You'll get there.

Afterall, there are still 25 days 'til Feb 7.