Moving with the PDGF ("transfer, go, on...")
As for the yet-to-be-completed tasks, per the first page of the post:
? Node 2 Outfitting: EV1 installs handrails, WIFs, gap spanners, and trunnion covers; and removes CBM pip pins and petal restraints. EV1 continues until EV3 is complete with S1 SFU config, MBSU jumper reconfig, and RPCM R&R. Then both begin PDGF install. ? RPCM S04B-C R&R: EV3 removes the failed RPCM, unstows the new RPCM from its ORU bag, and installs the new RPCM. The failed RPCM is brought back in the airlock in the same ORU bag. ? PDGF Install on Node 2: Both EVs remove the PDGF from its temp stowed location tethered to Node 2, and install the PDGF using EDFs and horseshoe connectors. This task is required for Node 2 relocation to Lab Fwd. ? Node 2 Outfitting (cont): Once PDGF install is complete, both EVs finish Node 2 outfitting tasks that were not completed earlier. ? EVA Cleanup/Ingress: The crew translates back to the airlock, performs tool inventory, ingresses the airlock, and closes the hatch.