Quote from: russianhalo117 on 01/20/2022 06:04 amJoint Press Briefing:I watched this live. I don't speak Japanese and so got very little out of it, but there were a couple animation which were helpful. It seems that the LE-9 engine problem, which is going to keep H3 grounded for at least this quarter, involves the turbopump blade resonating. In the presentation, there was an animation where it looked like it was warping.Here's the official documentation, which I'll probably run through google translate in a bit.https://www.jaxa.jp/press/2022/01/20220121-1_j.html
Joint Press Briefing:
H3 September 1st 1330 to 1500 JST Update:
Quote from: russianhalo117 on 09/01/2022 05:06 pmH3 September 1st 1330 to 1500 JST Update:Relying on machine translation, but they do appear to still be aiming for a first launch in 2022.
2022年度の打上げを目指し、H3ロケット試験機1号機再始動。H3 has got back on track toward its first flight in FY2022
Iwao Igarashi, MHI: found good solution to turbine vibration problems in engine for H3, proved it was effective. First H3 launch now projected this fiscal year (ends March 31); will announce date after static-fire tests in November. [Sep 13]
[H3 rocket today's photo]"Satellite Fairing Coupling Operation (VOS)" has been released.Please take a look.https://fanfun.jaxa.jp/countdown/h3/index.html
[H3 Rocket Topics]"On approaching the final stage of development" has been released!Project Manager Okada will tell you about the scene and preparations for the final stage of development.Please take a look.fanfun.jaxa.jp/countdown/h3/i…#H3 #ロケット
[press release]Implementation of H3 Rocket Test Vehicle No. 1 1st Stage Actual Tank Stage Combustion Test
Implementation of H3 Rocket Test Vehicle No. 1 1st Stage Actual Tank Stage Combustion TestNovember 2, 2022Japan Aerospace Exploration AgencyThe Japan Aerospace Exploration Agency (JAXA) will conduct the first-stage actual tank stage combustion test as follows as part of the development test for the launch of the H3 rocket test vehicle No. 1 in 2022. ,i will let you know.RecordTest purpose : Comprehensive confirmation of 1st stage propulsion system using actual tankContents of the test : Combining the actual tank and the LE-9 engine, the LE-9 engine is combusted in the same procedure as during launch, and the overall function is confirmed.Implementation period : Sunday, November 6, 2022 to Monday, November 7, 2022Location : Tanegashima Space Center Large rocket launch sitePlease note that the test implementation period may change depending on the weather and work progress.
The aircraft [rocket] movement started at 18:30 as scheduled, and it took about 30 minutes to arrive at LP2.
H3 test machine No. 1 CFT specification that appeared from VAB.
ML5 lower dolly fairing air conditioning truck.
H3 test machine arriving at LP2."Daichi 3" and the logo of the Defense Acquisition Agency on the brand new short fairing.
H3 rocket test machine No. 1 CFTFrom 16:30 on November 6th#CFT#H3ロケット試験機1号機
After all, the power of LE-9 x 2 units is amazing.