Author Topic: ET-118 latest  (Read 3182 times)

Online Chris Bergin

ET-118 latest
« on: 01/27/2006 03:37 pm »
ET-118 in Horizontal Final Assembly, Position 1

Developmental Flight Instrumentation (DFI)
 Currently working engineering for LH2 and LO2 DFI.
Longeron Closeout R&R
Preparations for longeron proficiency sprays continue.  ET-118 surface preps continue.
PAL Ramp
Removal of LH2 PAL ramp completed week of 1/16. Completed zone layout for the LO2 PAL ramp removal.