Our auditors found that long-standing issues related to NASA’s management of #SLS contracts for the RS-25 Engines and Boosters—the two components that will power the mega rocket to space—have contributed to $6 billion in increased costs and delays of 6 years.
WHAT WE FOUNDNASA continues to experience significant scope growth, cost increases, and schedule delays on its booster and RS-25 engine contracts, resulting in approximately $6 billion in cost increases and over 6 years in schedule delays above NASA’s original projections. These increases are caused by long-standing, interrelated issues such as assumptions that the use of heritage technologies from the Space Shuttle and Constellation Programs were expected to result in significant cost and schedule savings compared to developing new systems for the SLS. However, the complexity of developing, updating, and integrating new systems along with heritage components proved to be much greater than anticipated, resulting in the completion of only 5 of 16 engines under the Adaptation contract and added scope and cost increases to the Boosters contract. While NASA requirements and best practices emphasize that technology development and design work should be completed before the start of production activities, the Agency is concurrently developing and producing both its engines and boosters, increasing the risk of additional cost and schedule increases.Additionally, Marshall Space Flight Center procurement officials who oversee all four contracts are challenged by inadequate staff, their lack of experience, and limited opportunities to review contract documentation. Specifically, inadequate procurement management led us to question $24.5 million in payments to Northrop Grumman to resolve a disputed request for equitable adjustment (REA) of award fee payments. Marshall procurement officials also encountered significant issues with the award of BPOC, the follow-on booster contract, which started as an undefinitized letter contract in which terms, specifications, and price were not agreed upon before performance began. We found NASA took 499 days to definitize the letter contract, which is far outside the 180-day federal guidance. At definitization, BPOC also lacked scope details, omitted key contract clauses, underwent a limited legal review, and is at risk of making duplicate payments for overlapping work performed under BPOC and the upcoming Exploration Production and Operations Contract. We also questioned an additional $5.6 million payment NASA made to Northrop Grumman related to the Agency’s improper liquidation of funds.Further, NASA used cost-plus contracts at times where we believe fixed-price contracts should have been considered to potentially reduce costs, including the addition of 18 new production engines under the RS-25 Restart and Production contract and acquisition of Artemis IV booster long-lead materials under the BPOC letter contract. In addition, contractors did not receive accurate performance ratings in accordance with federal requirements, such as the “very good” rating awarded to Aerojet Rocketdyne on the end-item Adaptation contract despite only finishing 5 of 16 engines. As a result, we question $19.8 million in award fees it received for the 11 unfinished engines which were subsequently moved to the RS-25 Restart and Production contract and may now be eligible to receive additional award fees.Faced with continuing cost and schedule increases, NASA is undertaking efforts to make the SLS more affordable. Under the RS-25 Restart and Production contract, NASA and Aerojet Rocketdyne are projecting manufacturing cost savings of 30 percent per engine starting with production of the seventh of 24 new engines. However, those savings do not capture overhead and other costs, which we currently estimate at $2.3 billion. Moreover, NASA currently cannot track per-engine costs to assess whether they are meeting these projected saving targets.WHAT WE RECOMMENDEDTo increase transparency, accountability, and oversight of the SLS booster and engine contracts and NASA’s affordability efforts, and ensure duplicative award fees are not earned, we recommended NASA senior leadership: (1) assess whether the 18 new RS-25 production engines under the RS-25 Restart and Production contract can be adjusted to fixed price; (2) identify procurement needs and resources available to address staff shortages at Marshall; (3) ensure Marshall officials comply with best practices for establishing and maintaining internal controls related to REAs, fiscal law, and appropriate internal and external engagement; (4) ensure appropriate separation of program and procurement actions and compliance with federal requirements for use of letter contracts, proper definitization, overpayments, and duplicative payments of award fees for modified scope and contracts; (5) update RS-25 production per engine cost estimates to include investments in production restart; (6) review and update BPOC’s scope of work and technical requirements needed to complete the respective periods of performance; (7) review BPOC’s definitization to ensure proper liquidation of funds paid under the letter contract; and ( develop a separate non-fee bearing contract line item for completion of the 11 unfinished heritage RS-25 adaptation engines.We provided a draft of this report to NASA management, who concurred with Recommendations 1, 2, 3, 6, and 7, and partially concurred with Recommendations 4, 5, and 8. We consider management’s comments responsive to all eight recommendations, and therefore the recommendations are resolved and will be closed upon completion and verification of the proposed corrective actions. Despite concurring and partially concurring with all eight recommendations, the Associate Administrator for Exploration Systems Development Mission Directorate’s and Assistant Administrator for Procurement’s response to the draft of this report stated that the directorate and program do not concur with the facts as presented in the body of the report. We take issue with this summary characterization and are disappointed that the Agency’s formal response failed to specify the facts with which it disagrees. Consistent with professional standards, we carefully considered management’s technical comments to our draft and, when sufficiently supported, incorporated that information in the final report.
YIKES. "NASA continues to experience significant scope growth, cost increases, and schedule delays on its booster and RS-25 engine contracts, resulting in approximately $6 billion in cost increases and over 6 years."oig.nasa.gov/docs/IG-23-015…
NASA has spent as much on cost *increases* for SLS rocket boosters and engines as it is spending on two fully reusable lunar landers. LOL. Cost-plus contracts, baby!
Amazing. "The cost impact from these four contracts increases our projected cost of each SLS by $144 million through Artemis IV, increasing a single Artemis launch to at least $4.2 billion."
For example, NASA initially awarded the RS-25 Restart and Production contract for six new production engines under a cost-plus structure. Approximately 3 years later, the contract was modified to include an additional 18 production engines valued at $1.8 billion. Given its established design, purchase of these additional engines could have been structured under a fixed-price contract....
NASA has a lot to say. At the bottom of the report: “As a result, the directorate and the program do not concur with, not endorse, the facts as presented in the body of the report.”👀
Government Accountability Office (GAO), as was the case with the SLS program in the present audit. While both directorate and program leadership welcome the healthy debate and dispositioning of comments that accompany these engagements, they are concerned that the foregoing report offers an incomplete view of the program's decision-making regarding its boosters and engines elements and that the information in the report is presented without the context that would have rendered it more accurate. Despite several hours of follow-up meetings with the OIG team following the release of the initial draft report and submission of extensive supporting documentation by the SLS program, NASA leadership was disappointed to see that few of the clarifications offered by the Agency's subject-matter experts were incorporated herein. As a result, the directorate and the program do not concur with, nor endorse, the facts as presented in the body of the report.Nonetheless, the program does concur or partially concur with the recommendations provided by the OIG since much of the suggested work was either already completed or scheduled prior to the initiation of the audit. It is evident that the OIG and directorate and program leadership agree on several key principles: major acquisitions and contract management practices should continue to be reviewed at the highest levels of leadership to ensure the Federal Acquisitions Regulation (FAR) is faithfully employed, accountability and oversight is rigorously practiced, and maximum transparency is evident in contract execution. NASA will continue to welcome engagements with audit teams while pushing forward its priority the development, production, and testing of hardware for the next Artemis mission in a responsible manner.
A final note: The Associate Administrator for Exploration Systems Development Mission Directorate’s and Assistant Administrator for Procurement’s response to the draft of this report stated that NASA leadership “was disappointed to find that few of the clarifications offered by the Agency’s subject matter experts were incorporated herein” and thus “the directorate and the program do not concur with, nor endorse, the facts as presented in the body of the report.” We take issue with this summary characterization and are disappointed that in its formal response the Agency failed to specify the facts in the report with which it disagrees. Consistent with professional standards, we carefully considered management’s technical comments to our draft and, when sufficiently supported, incorporated that information in the final report. Further, we had multiple additional discussions with senior Agency officials at Headquarters and Marshall about the report’s findings. However, from our perspective personnel involved in these conversations did not provide evidence to fundamentally change our findings and recommendations. In addition, in conducting this audit we followed the quality control procedures required by government auditing standards, including ensuring the report received an independent verification of its findings and supporting evidence by auditors unconnected with this review.
I just don't understand the continued use of cost plus contracts for finished designs. Cost plus might make sense for the first 1 or 2 when the design is not certain and changes are needed, after that it's just a recipe for waste. And the fact that they can't track the costs per engine build is just criminal.
Past time to can Free and Horne…
Recommendation 1: Assess whether the 18 new RS-25 production engines under the RS-25 Restart and Production contract can be adjusted from cost-plus to fixed-price.Management’s Response: NASA concurs with this recommendation. Before initiating the RS-25 Production Restart contract, an assessment was conducted to determine the most cost-effective contract type. Due to the high amount of development, test, and engineering design work associated with the restart of new production lines and qualification of new manufacturing processes, we assessed that cost risk would have driven the contractor to propose an unaffordable fixed-price cost to cover their identified risk; therefore, a cost-plus-incentive-fee contract was determined to be more cost effective and to provide additional insight. As currently structured, a cost-type arrangement affords the Government the opportunity to monitor cost efficiencies and risk and ultimately discontinue development if deemed unaffordable or unachievable from a technical perspective. A fixed-price contract does not equate to reduced costs; in development work, it can have the opposite effect if entered with high uncertainty in cost and/or technical requirements.
Fixed costs doesn't work because the companies would ask an exorbitant fixed price. The whole procurement method is flawed. Instead of fixed cost, NASA ended up implementing fixed cost plus incentives which is better than cost plus.
Recommendation 1: Assess whether the 18 new RS-25 production engines under the RS-25 Restart and Production contract can be adjusted from cost-plus to fixed-price.Management’s Response: NASA concurs with this recommendation. Before initiating the RS-25 Production Restart contract, an assessment was conducted to determine the most cost-effective contract type. Due to the high amount of development, test, and engineering design work associated with the restart of new production lines and qualification of new manufacturing processes, we assessed that cost risk would have driven the contractor to propose an unaffordable fixed-price cost to cover their identified risk; ...
Quote from: VSECOTSPE on 05/25/2023 08:35 pmPast time to can Free and Horne…Fixed costs doesn't work
Quote from: WindnWar on 05/25/2023 08:56 pmI just don't understand the continued use of cost plus contracts for finished designs. Cost plus might make sense for the first 1 or 2 when the design is not certain and changes are needed, after that it's just a recipe for waste. And the fact that they can't track the costs per engine build is just criminal.I smell Pork.
Quote from: yg1968 on 05/25/2023 11:07 pmQuote from: VSECOTSPE on 05/25/2023 08:35 pmPast time to can Free and Horne…Fixed costs doesn't work I did not write anything about contract cost structure. I only wrote that Free and Horne should be shown the door.
Quote from: yg1968 on 05/25/2023 11:07 pmFixed costs doesn't work because the companies would ask an exorbitant fixed price. The whole procurement method is flawed. Instead of fixed cost, NASA ended up implementing fixed cost plus incentives which is better than cost plus. Sorry, no. Two distinct efforts in play: production restart and ongoing production.Quote from: page 52 of the OIG ReportRecommendation 1: Assess whether the 18 new RS-25 production engines under the RS-25 Restart and Production contract can be adjusted from cost-plus to fixed-price.Management’s Response: NASA concurs with this recommendation. Before initiating the RS-25 Production Restart contract, an assessment was conducted to determine the most cost-effective contract type. Due to the high amount of development, test, and engineering design work associated with the restart of new production lines and qualification of new manufacturing processes, we assessed that cost risk would have driven the contractor to propose an unaffordable fixed-price cost to cover their identified risk; ...That is BS. Might apply to production restart, but not subsequent ongoing production.NASA folded for whatever reason; they need to grow some balls.
Why? Most of this pre-dates them.
Quote from: VSECOTSPE on 05/25/2023 08:35 pmPast time to can Free and Horne…Fixed costs doesn't work because the companies would ask an exorbitant fixed price.
The whole procurement method is flawed.
Instead of fixed cost, NASA ended up implementing fixed cost plus incentives which is better than cost plus.
Marshall procurement officials also encountered significant issues with the award of BPOC, the follow-on booster contract, which started as an undefinitized letter contract in which terms, specifications, and price were not agreed upon before performance began. We found NASA took 499 days to definitize the letter contract, which is far outside the 180-day federal guidance.
In addition, contractors did not receive accurate performance ratings in accordance with federal requirements, such as the “very good” rating awarded to Aerojet Rocketdyne on the end-item Adaptation contract despite only finishing 5 of 16 engines. As a result, we question $19.8 million in award fees it received for the 11 unfinished engines which were subsequently moved to the RS-25 Restart and Production contract and may now be eligible to receive additional award fees.
Past time to can Free and Jackson…
Fixed costs doesn't work because the companies would ask an exorbitant fixed price....
And while you're at it, please show Nelson the door as well. He's in large part responsible for starting the bottomless pit that is SLS.
A couple of thoughts from someone that has been on the contractor side of government contracts:1. NASA is already paying exorbitant prices for their hardware, so your logic doesn't hold up.
Don't pat yourself on the back too quickly, because you don't know what the incentive schedule was for the fixed cost plus incentives option.
Unlike a cost-plus contract, [under a cost-plus-incentive fee contract] the cost in excess of the target cost is only partially paid according to a Buyer/Seller ratio, so the seller's profit decreases when exceeding the target cost. Similarly, the seller's profit increases when actual costs are below the target cost defined in the contract.
Quote from: VSECOTSPE on 05/25/2023 08:35 pmPast time to can Free and Jackson…And while you're at it, please show Nelson the door as well. He's in large part responsible for starting the bottomless pit that is SLS.
...In any event, from what I have read, the incentives under a cost plus incentive fee contract are incentives to reduce cost, so it is better than a regular cost plus contract. ...
Quote from: yg1968 on 05/26/2023 01:24 amWhy? Most of this pre-dates them.Free became Exploration AA in 9/21. Before Free, BPOC was $199M. Two months after Free, it was $3.2B. And the contract still had undefinitized terms, which remain undefinitized to this day! RS-25 Restart and Production tripled to $3.6B by 6/22. There was another $102M of cost growth and 17 months of schedule slip thru 10/22. IG testified 3/22 that each Orion/SLS thru Artemis IV would be $4.1B. Now barely a year later it’s $144M more just from SLS increases alone. Free’s budget profligacy is a long-standing issue.
It's hard for Free to look good with SLS and Orion as it relates to costs.
But Free's interventions have not all been...
has also been involved with Appendix P
(he was the selecting officer)
and the upcoming LTV
(both services contract).
He also insisted that NASA have more than one base camp which is an improvement.
However, there is room for improvement in determining the contributions of each international partner. It's taking longer than expected to finalize the agreements.
The contract type doesn’t matter if leadership doesn’t have basic development program management chops. Free does not. If he sticks around for years to come, Blue Moon and LTV will augur in, too.
Last I knew, Free stated that they were looking at some camper model — not that he was insisting on one strategy over another.
I disagree, I think that the procurement method makes the results predictable.
I don't think that SLS and Orion will be successes regardless who is the AA because they are not.
Perhaps, Free is to blame for SLS costing $200m more than before but it was already $4.1B before this new IG report came out.
The camper model seems to be out. Free is now saying that the Italian Space Agency will likely be providing 3 separate habitats at different locations in order to have multiple landing locations which helps because of the lighting conditions on the south pole.
Quote from: Coastal Ron on 05/26/2023 05:17 amA couple of thoughts from someone that has been on the contractor side of government contracts:1. NASA is already paying exorbitant prices for their hardware, so your logic doesn't hold up.... For fixed cost to work properly, you need to have competition. If you don't, the sole-source company can ask whatever price that they want (fixed price or not). That is why I said that the whole procurement is flawed. A services procurement with competition would be better.
Quote from: yg1968 on 05/27/2023 01:32 pmI disagree, I think that the procurement method makes the results predictable. Not really. See Starliner.Fixed cost mainly limits the govt’s downside. But bad management at the contractor or agency level will still result in long delays, costly overruns that someone has to eat, and junky hardware.
Quote from: VSECOTSPE on 05/27/2023 01:55 pmQuote from: yg1968 on 05/27/2023 01:32 pmI disagree, I think that the procurement method makes the results predictable. Not really. See Starliner.Fixed cost mainly limits the govt’s downside. But bad management at the contractor or agency level will still result in long delays, costly overruns that someone has to eat, and junky hardware.Despite its problems, Starliner is still a lot better than SLS and Orion. Having said that the Starliner problems does show the importance of having more than one award.
This is why it is hard to have any enthusiasm for the Artemis program as currently structured. No amount of praise for the non-SLS hardware can overcome the shear amount of waste the SLS program is, and will continue to be.
Quote from: Coastal Ron on 05/27/2023 03:51 pmThis is why it is hard to have any enthusiasm for the Artemis program as currently structured. No amount of praise for the non-SLS hardware can overcome the shear amount of waste the SLS program is, and will continue to be. I disagree. I think that the HLS program will do the same to the Moon as commercial crew is doing for LEO.
Create an economy for these destinations by encouraging private non-NASA missions.
The Appendix P award is another step in the right direction in that respect.
You are just repeating NASA PR with the "economy" word. The only economy NASA will ever create with the Artemis program is here on Earth, by feeding money into NASA contractors. You can't create an economy in space until there is an exchange of currency IN SPACE that stays IN SPACE. NASA is not doing that with the Artemis program.
I’m not sure HLS does anything for SX and Starship that SX and Starship weren’t going to do eventually. HLS certainly accelerated Lunar Starship by some years, but I don’t think NASA funding is enabling for Lunar Starship like NASA funding enabled F9/Dragon at a much earlier point in SX history.
Blue is not the dynamic, risk-taking company that SX is, so I think an argument can be made that HLS funding is enabling for Blue Moon. But unlike Starship, Blue Moon is not an end-to-end human transport system. Unless Blue is also funded to develop a crew transport element to lunar orbit (which is probably dependent on Orion/SLS being drawn down), NASA’s investment in Blue Moon doesn’t open up the Moon, even if it is enabling for that lander.
Yeah, I can imagine a crew coming up on a Dreamchaser, transferring to a Blue Lagoon station, and then to a fueled Blue Moon landing stack and vice versa for a round trip to the lunar surface, a la 2001: A Space Odyssey. But that’s just me projecting desires, not reality. Until there’s a plan to do something like that with Blue Moon and that plan is funded, I’d stay skeptical.
Quote from: woods170 on 05/26/2023 08:37 amAnd while you're at it, please show Nelson the door as well. He's in large part responsible for starting the bottomless pit that is SLS.I wish. Senator Administrator Monster Rocket has been an adequate caretaker of what was essentially the Bridenstine plan at exit, i.e., onboard a second lander contractor. But besides publicly grouching about ML-2, he’s done little to improve the survivability of the Artemis Program going forward. And by letting the cancer of Orion/SLS cost growth spread unabated, he’s arguably leaving Artemis in a worse position than when he started. His deputy’s effort on Artemis “goals” (and I use that term loosely) have also not positioned the program well for coming budget battles.
Quote from: Coastal Ron on 05/28/2023 03:06 amYou are just repeating NASA PR with the "economy" word. The only economy NASA will ever create with the Artemis program is here on Earth, by feeding money into NASA contractors. You can't create an economy in space until there is an exchange of currency IN SPACE that stays IN SPACE. NASA is not doing that with the Artemis program.An economy isn't defined by where money is exchanged......https://en.wikipedia.org/wiki/Economy
As to the RS-25 and SRMs, and the very clear evidence that the contractors are milking the U.S. Taxpayer, does anyone think Congress will care? That this will be a "straw", to be added to the many that could eventually lead to a "last straw" for the SLS?
Despite your and VSECOTSPE’s logic, there is absolutely no hope that this mess will be reformed from within
The only answer is the end run, and frankly (distastefully to many) that means Musk/SpaceX.
Meanwhile, SLS will roll on until Congress finds a convenient way to shift their favorites onto other lucrative pit-digging operations for taxpayer dollars.
Quote from: yg1968 on 05/28/2023 04:43 amQuote from: Coastal Ron on 05/28/2023 03:06 amYou are just repeating NASA PR with the "economy" word. The only economy NASA will ever create with the Artemis program is here on Earth, by feeding money into NASA contractors. You can't create an economy in space until there is an exchange of currency IN SPACE that stays IN SPACE. NASA is not doing that with the Artemis program.An economy isn't defined by where money is exchanged......https://en.wikipedia.org/wiki/EconomyActually if you read that Wikipedia article, it does. But going into it would OT, so move along...
Economic transactions occur when two groups or parties agree to the value or price of the transacted good or service, commonly expressed in a certain currency. However, monetary transactions only account for a small part of the economic domain.
... quotes ...Congress cares about the Orion/SLS workforce. Provide that workforce with other, more useful tasks (there’s plenty to pick from in a real human space exploration effort) and the Gordian knot of the Apollo/STS infrastructure/workforce that has bedeviled NASA since Goldin can be untied. But if an administration fails to address the workforce as the Obama White House did, Congress will likely just shove another iteration of STS/Ares V/SLS down the agency’s throat.
Quote from: VSECOTSPE on 05/29/2023 06:27 pm... quotes ...Congress cares about the Orion/SLS workforce. Provide that workforce with other, more useful tasks (there’s plenty to pick from in a real human space exploration effort) and the Gordian knot of the Apollo/STS infrastructure/workforce that has bedeviled NASA since Goldin can be untied. But if an administration fails to address the workforce as the Obama White House did, Congress will likely just shove another iteration of STS/Ares V/SLS down the agency’s throat.Is the workforce argument as strong as it was 14 years ago though? Certainly commercial space has way way bigger share of US space workforce than it was back then. I doubt the "we must preserve shuttle technology" will be as compelling.
Quote from: Coastal Ron on 05/29/2023 03:18 pmQuote from: yg1968 on 05/28/2023 04:43 amQuote from: Coastal Ron on 05/28/2023 03:06 amYou are just repeating NASA PR with the "economy" word. The only economy NASA will ever create with the Artemis program is here on Earth, by feeding money into NASA contractors. You can't create an economy in space until there is an exchange of currency IN SPACE that stays IN SPACE. NASA is not doing that with the Artemis program.An economy isn't defined by where money is exchanged......https://en.wikipedia.org/wiki/EconomyActually if you read that Wikipedia article, it does. But going into it would OT, so move along... It says that it only accounts for a small part of the economic domain:Quote from: WikipediaEconomic transactions occur when two groups or parties agree to the value or price of the transacted good or service, commonly expressed in a certain currency. However, monetary transactions only account for a small part of the economic domain.
A given economy is a set of processes that involves its culture, values, education, technological evolution, history, social organization, political structure, legal systems, and natural resources as main factors. These factors give context, content, and set the conditions and parameters in which an economy functions. In other words, the economic domain is a social domain of interrelated human practices and transactions that does not stand alone.
Quote from: yg1968 on 05/29/2023 07:18 pmQuote from: Coastal Ron on 05/29/2023 03:18 pmQuote from: yg1968 on 05/28/2023 04:43 amQuote from: Coastal Ron on 05/28/2023 03:06 amYou are just repeating NASA PR with the "economy" word. The only economy NASA will ever create with the Artemis program is here on Earth, by feeding money into NASA contractors. You can't create an economy in space until there is an exchange of currency IN SPACE that stays IN SPACE. NASA is not doing that with the Artemis program.An economy isn't defined by where money is exchanged......https://en.wikipedia.org/wiki/EconomyActually if you read that Wikipedia article, it does. But going into it would OT, so move along... It says that it only accounts for a small part of the economic domain:Quote from: WikipediaEconomic transactions occur when two groups or parties agree to the value or price of the transacted good or service, commonly expressed in a certain currency. However, monetary transactions only account for a small part of the economic domain.*Sigh*The paragraph preceding that gives you the answer, which is:QuoteA given economy is a set of processes that involves its culture, values, education, technological evolution, history, social organization, political structure, legal systems, and natural resources as main factors. These factors give context, content, and set the conditions and parameters in which an economy functions. In other words, the economic domain is a social domain of interrelated human practices and transactions that does not stand alone.The Artemis program is a science expedition, not a location where "interrelated human practices and transactions" will occur.You want to debate this more, PM me. Otherwise let's get back to the topic at hand, which is that yet ANOTHER non-biased investigation of the SLS program has found rampant mismanagement and overpayments to contractors. This will only end when the SLS program is ended...
I struggle to find (as in I want to believe there is) a benefit to Artemis that outweighs the $50 billion sunk into Orion/SLS/EGS through last year:https://www.planetary.org/space-policy/cost-of-sls-and-orionI just don’t see it. The relative pittance planned to be spent on landers ($6 billion) and other surface systems (few billion?) is bass ackwards. And even if it wasn’t, those lunar activities are heavily constrained by a mission rate of one crew of four every year or two. And even if there was a better ratio of transport to actual lunar activity, there’s no clear articulation in Melroy’s goals of what that lunar activity is supposed to deliver, certainly nothing worth some handful of tens of billions of dollars.I wish it were otherwise, but so far, no justification/rationale or capability/achievement for Artemis has been put forth that is commensurate with its cost.
They should contract for services like they have done for HLS and commercial crew, etc.
Quote from: VSECOTSPE on 05/28/2023 05:13 am...I wish it were otherwise, but so far, no justification/rationale or capability/achievement for Artemis has been put forth that is commensurate with its cost.Artemis inherited SLS and Orion.
...I wish it were otherwise, but so far, no justification/rationale or capability/achievement for Artemis has been put forth that is commensurate with its cost.
The rest of Artemis: the Artemis Accords, HLS, the Spacesuits, CLPS, the LTV are all great programs or agreements that can and should survive SLS and Orion. The Moon to Mars goals and strategies are fine but in the end what really matters are the programs that are associated with these objectives and the programs are good.
No, the Artemis program was built on top of the SLS+Orion.Prior to the V.P. Pence announcing the 2024 Moon landing goal, SLS supporters (including those on NSF) had been claiming that the SLS was a "Moon rocket", and obviously the Orion as-built can only make it to the Moon, so the SLS+Orion were perceived as the only option to allow a Moon landing by the end of a potential second Trump Administration. There was simply no other option for making the 2024 politically-oriented date.
It doesn't look like Congress agrees with your assessment, since Congress continues to dump money into the SLS, regardless of the MANY warnings that U.S. Taxpayer money is NOT being economically spent. Because the goal that Congress has for the Artemis program is not what your goal is - everything BUT the SLS+Orion are just secondary to spending money on the right large NASA contractors, as the cost overruns on the RS-25 and booster show.If Congress truly cared about the Artemis program then they would care about WHY the SLS & Orion program costs so much, are NOT meeting their planned schedule goals, and CANNOT provide a meaningful Artemis mission tempo without massive budget increases. In other words, Congress would care about what it would take to make the Artemis program more than a flags & footprints exercise...
Bridenstine was essentially forced by Shelby to conclude that SLS was the only way to go but it was obvious that there was other options including Falcon Heavy and Orion which NASA had started to look at.
Quote from: yg1968 on 05/31/2023 02:50 pm Bridenstine was essentially forced by Shelby to conclude that SLS was the only way to go but it was obvious that there was other options including Falcon Heavy and Orion which NASA had started to look at. I think that what happened to Kathy Lueders was a pretty good sign that "other options" were not actually on the table no matter how much they appeared to be.
Quote from: tea monster on 05/31/2023 08:21 pmQuote from: yg1968 on 05/31/2023 02:50 pm Bridenstine was essentially forced by Shelby to conclude that SLS was the only way to go but it was obvious that there was other options including Falcon Heavy and Orion which NASA had started to look at. I think that what happened to Kathy Lueders was a pretty good sign that "other options" were not actually on the table no matter how much they appeared to be.That happened after Bridenstine left, under the new Administration. However, if your point is that Congress never would have accepted a non-SLS-solution, I agree with that.
SLS was originally supposed to use off the shelf components. Boosters, SSME, and RL-10's on the upper. They spent a lot developing the 5 segment solids, a lot on changing the SSME to RS-25's, and a lot on developing the J2X that they didn't or haven't used. Direct had the right approach. Use what they had until Jupiter could evolve. Spending some money to manufacture the RD-180 in America and making an 8-10 engine RD-180 booster with a J2X upper stage would have been cheaper and given the same or better results. This booster could have been made reusable using F9 technology. Solids are heavy and expensive and cost as much to refurbish as new ones. Core and RS-15's are expendable and expensive. No clear way to evolve into a reusable rocket.
I have not followed the engine saga for the RS-25s. Please correct me if I have missed something - at what point did they realise that they did not have enough shuttle engines to fulfil the SLS program? I would have thought that this point would come up pretty early in planning the SLS. In descriptions of the development of the SLS it seems to be almost an afterthought that they would need to somehow come up with more SSMEs to keep the program going. If I've missed something, I'm sorry.
Quote from: tea monster on 05/31/2023 11:00 pmI have not followed the engine saga for the RS-25s. Please correct me if I have missed something - at what point did they realise that they did not have enough shuttle engines to fulfil the SLS program? I would have thought that this point would come up pretty early in planning the SLS. In descriptions of the development of the SLS it seems to be almost an afterthought that they would need to somehow come up with more SSMEs to keep the program going. If I've missed something, I'm sorry.IIRC there was some consideration of using the RS-68 instead of the SSME/RS-25, but once they decided to use the SSME/RS-25 they would have known that they were going to need to build more engines.As a note, Aerojet Rocketdyne makes both the RS-68 (used on Delta IV) and the SSME/RS-25, so the SLS program was going to provide guaranteed work for them regardless which was chosen.
Quote from: Coastal Ron on 05/31/2023 11:39 pmQuote from: tea monster on 05/31/2023 11:00 pmI have not followed the engine saga for the RS-25s. Please correct me if I have missed something - at what point did they realise that they did not have enough shuttle engines to fulfil the SLS program? I would have thought that this point would come up pretty early in planning the SLS. In descriptions of the development of the SLS it seems to be almost an afterthought that they would need to somehow come up with more SSMEs to keep the program going. If I've missed something, I'm sorry.IIRC there was some consideration of using the RS-68 instead of the SSME/RS-25, but once they decided to use the SSME/RS-25 they would have known that they were going to need to build more engines.As a note, Aerojet Rocketdyne makes both the RS-68 (used on Delta IV) and the SSME/RS-25, so the SLS program was going to provide guaranteed work for them regardless which was chosen.Yup. But IIRC that was squashed cuz RS-68: (1) Had no relationship to Shuttle. Which, as we all know would have violated the raison d'être of SLS continuing on with reusing Shuttle legacy parts (*cough*). (2) Would have to be human rated (a long history of yes-no-maybe with RS-68). (3) The heat flux and ablative nozzles in proximity to the SRB's would likely have been problematic. (4) ...In any case, those issues were recognized fairly early on. And much of the rework to use RS-68's likely would have landed outside of AJR. So path of least resistance (*cough*), RS-25 it wuz and is.
It's very simple ...
Artemis inherited SLS and Orion.
The rest of Artemis: the Artemis Accords, HLS, the Spacesuits, CLPS, the LTV are all great programs or agreements that can and should survive SLS and Orion.
The Moon to Mars goals and strategies are fine but in the end what really matters are the programs that are associated with these objectives and the programs are good.
Artemis is not worth $8B/yr. and tens of thousands of aerospace careers for that. There’s literally nothing they can do or that would grow out of their activities that would ever be remotely commensurate with those costs. It’s a really expensive stunt.
The Accords, CLPS, and the Starship half of HLS all largely exist independently of the program. The Artemis budget could disappear tomorrow and those three elements would continue based on rounding in the HQ overhead budget (Accords), what Planetary Science wants/needs (CLPS), and StarLink revenue/SpaceX deep pockets (Starship).If they’re only going to be used once every 2-3 or 4-6 years, the suits, the second lander, and the LTV aren’t worth it. Yeah, they’re fixed-price contracts so the government’s downside is limited unlike Orion/SLS. But that doesn’t mean that the money being spent on them can produce anything commensurate with their costs under such limited usage. And to be realistic, even these fixed-price contracts don’t open up frontiers without a SpaceX-like organization on the other end. Antares and Starliner attest to that, and so far there’s no with SpaceX’s combination of organizational drive, technical competence, and deep pockets amongst these contractors. (As much as I wish we were not relying so much on SpaceX.)
The program is likely facing 7% cuts starting in 2024, and the Deputy Administrator’s documents provide no clarity on where priorities lie and what should go and what should stay.
I disagree that it is a stunt and I think that it is worth it even at $8B per year.
Only one company has to succeed in finding non-NASA clients for the program to be successful.
Where do you get your 7% cut? From what I have read discretionary spending will be frozen in FY24 and will get a 1% increase in FY25.
Quote from: yg1968 on 06/07/2023 01:08 pmOnly one company has to succeed in finding non-NASA clients for the program to be successful.So for the RS-25 and booster overruns to be looked at as good investments, and not corporate pork, all we need is for SpaceX to sign up a non-NASA customer? And then all sins are washed away?And yeah, you may have been WAY off topic and talking about things not related specifically to the SLS cost overruns, but it is all related. Because as long as the SLS is justified as being required for the Artemis program, then massive cost overruns will continue to be ignored.When do rational people get a voice in all of this? When will Congress do their job and ask NASA to reassess their use of the SLS due to the enormous cost and likelihood of lower cost alternatives?THAT is the topic being debated here.
Quote from: Coastal Ron on 06/07/2023 04:26 pmQuote from: yg1968 on 06/07/2023 01:08 pmOnly one company has to succeed in finding non-NASA clients for the program to be successful.So for the RS-25 and booster overruns to be looked at as good investments, and not corporate pork, all we need is for SpaceX to sign up a non-NASA customer? And then all sins are washed away?And yeah, you may have been WAY off topic and talking about things not related specifically to the SLS cost overruns, but it is all related. Because as long as the SLS is justified as being required for the Artemis program, then massive cost overruns will continue to be ignored.When do rational people get a voice in all of this? When will Congress do their job and ask NASA to reassess their use of the SLS due to the enormous cost and likelihood of lower cost alternatives?THAT is the topic being debated here.My comment was in the context of what VSECOTSPE said about Boeing and Antares.
Quote from: yg1968 on 06/07/2023 04:40 pmQuote from: Coastal Ron on 06/07/2023 04:26 pmQuote from: yg1968 on 06/07/2023 01:08 pmOnly one company has to succeed in finding non-NASA clients for the program to be successful.So for the RS-25 and booster overruns to be looked at as good investments, and not corporate pork, all we need is for SpaceX to sign up a non-NASA customer? And then all sins are washed away?And yeah, you may have been WAY off topic and talking about things not related specifically to the SLS cost overruns, but it is all related. Because as long as the SLS is justified as being required for the Artemis program, then massive cost overruns will continue to be ignored.When do rational people get a voice in all of this? When will Congress do their job and ask NASA to reassess their use of the SLS due to the enormous cost and likelihood of lower cost alternatives?THAT is the topic being debated here.My comment was in the context of what VSECOTSPE said about Boeing and Antares.Yes, and the Starliner, Cygnus, and Orbital Reef programs are NOT the topic here, the RS-25 and boosters are. There are other threads for those programs.Do you have anything to say about the SLS program RS-25 or boosters cost issues the OIG uncovered?