Poll

Should Briz be re-designed, or should Khrunichev focus on quality control?

Re-design
7 (20.6%)
Quality control
27 (79.4%)
Switch to another upper stage
0 (0%)

Total Members Voted: 34

Voting closed: 12/14/2012 04:35 pm

Author Topic: Fixing Briz  (Read 14783 times)

Offline Danderman

  • Extreme Veteran
  • Senior Member
  • *****
  • Posts: 10288
  • Liked: 699
  • Likes Given: 723
Fixing Briz
« on: 12/10/2012 04:35 pm »
I am specifically not listing the variants of Briz, because they all share the common problem of the thing not working.

The question is how to fix it?

The easiest approach is to upgrade quality control.

The second approach is to look at the entire existing propulsion system, and see if there is a re-design that would enhance the reliability of the entire existing system.

A third approach is more challenging -

a) rework the avionics so that in the event that a main engine failure is detected, rather than immediate separation of the satellite, the entire unit should go into safe mode.

b) institute an uplink command channel so that the stage could be commanded from the ground.

c) replumb the system so that the "settling" thrusters could be fed from the main propulsion tank, and thus serve as a backup to the main engine. This would be arduous, both in design, construction and operations, but preferable to losing a satellite once a year.

Of course, any change to the existing system creates risks, but I suspect that the risk from the change would be less than the current risk.

Offline kevin-rf

  • Elite Veteran
  • Senior Member
  • *****
  • Posts: 8823
  • Overlooking the path Mary's little Lamb took..
  • Liked: 1318
  • Likes Given: 306
Re: Fixing Briz
« Reply #1 on: 12/10/2012 05:41 pm »
a) rework the avionics so that in the event that a main engine failure is detected, rather than immediate separation of the satellite, the entire unit should go into safe mode.

b) institute an uplink command channel so that the stage could be commanded from the ground.

As you point out in 'b', 'a' requires uplink and assumes the "problem" can be fixed by simple uplink before the Briz's batteries die. This assumes the Briz is shutting down for silly reasons and not an unsafe state that could lead to a very rapidly evolving and exciting situation. I do not believe that is the case. 

In the sense of the paying customer, salvaging the payload through immediate separation and getting it the heck away from the stage is the safest option in an off nominal situation. 

What they need is a fool proof way to safe the stage in the event of these situations. A RUD some months later is not a good way to safe the stage.
« Last Edit: 12/10/2012 05:45 pm by kevin-rf »
If you're happy and you know it,
It's your med's!

Offline Danderman

  • Extreme Veteran
  • Senior Member
  • *****
  • Posts: 10288
  • Liked: 699
  • Likes Given: 723
Re: Fixing Briz
« Reply #2 on: 12/10/2012 06:03 pm »
a) rework the avionics so that in the event that a main engine failure is detected, rather than immediate separation of the satellite, the entire unit should go into safe mode.

b) institute an uplink command channel so that the stage could be commanded from the ground.

As you point out in 'b', 'a' requires uplink and assumes the "problem" can be fixed by simple uplink before the Briz's batteries die. This assumes the Briz is shutting down for silly reasons and not an unsafe state that could lead to a very rapidly evolving and exciting situation. I do not believe that is the case. 

In the sense of the paying customer, salvaging the payload through immediate separation and getting it the heck away from the stage is the safest option in an off nominal situation. 

What they need is a fool proof way to safe the stage in the event of these situations. A RUD some months later is not a good way to safe the stage.

I would imagine that an abort system could differentiate between a true emergency, where the spacecraft should be separated immediately, and a condition where the engine is shutting down in a relatively safe manner. And, yes, the a+b+c I listed above are not separate options, but instead an integrate approach to the problem.

IIRC, Briz does not have a unified fuel system, so there is a separate prop tank system for the small thrusters. Creating that unified fuel system would make Briz a more robust system, at the risk of a thruster leak impacting the entire prop supply.

Offline Prober

  • Senior Member
  • *****
  • Posts: 10348
  • Save the spin....I'm keeping you honest!
  • Nevada
  • Liked: 721
  • Likes Given: 729
Re: Fixing Briz
« Reply #3 on: 12/10/2012 06:08 pm »
Isn't the Briz in the middle of a redesign?

This is how the Russian system tests with launches? 

2017 - Everything Old is New Again.
"I fear all we have done is to awaken a sleeping giant..." --Isoroku Yamamoto

Offline Galactic Penguin SST

Re: Fixing Briz
« Reply #4 on: 12/10/2012 06:10 pm »
Well do we know what's going on at Khrunichev? For some reason the Fregat upper stage build by Lavochikin, which uses an engine with more or less the same parts and design, never had any in flight failures since its first flight in 2000 (and only one small ground processing issue that led to a slightly off course mission in 2009). Why? QA issues? Or just that a space tug with a pump fed engine that must work for 9 hours + is just difficult to work with high reliability?
Astronomy & spaceflight geek penguin. In a relationship w/ Space Shuttle Discovery. Current Priority: Chasing the Chinese Spaceflight Wonder Egg & A Certain Chinese Mars Rover

Offline kevin-rf

  • Elite Veteran
  • Senior Member
  • *****
  • Posts: 8823
  • Overlooking the path Mary's little Lamb took..
  • Liked: 1318
  • Likes Given: 306
Re: Fixing Briz
« Reply #5 on: 12/10/2012 06:38 pm »
I would imagine that an abort system could differentiate between a true emergency, where the spacecraft should be separated immediately, and a condition where the engine is shutting down in a relatively safe manner. And, yes, the a+b+c I listed above are not separate options, but instead an integrate approach to the problem.

Your assuming that the engine can, and should be restarted after the shutdown. These engines do not shutdown for no reason, if they are shutting down there is a reason, and short of getting a cosmonaut up there with a wrench they should not be restarted.

Also, while a a single propellant supply may make sense, the settling thruster thrust is so low that for every mission you would have to completely redesign the flight software to handle two completely different thrusting modes. Include the stage and thrusters need to live long enough   to burn a full tank of propellant. This burn will take much longer than one with the main engine. You are adding cost and complexity to the upper stage to fix something that should not be an issue.

Btw a list of Briz failures over the last few years:

2006 February 28 - Arabsat - 4M

14 March 2008 - Ruptured plumbing, you can not continue to use the system after that.

3 February 2011 - Engine restart failed, not a Proton GEO launch. Brings up a point, could it have handle the extra weight you are asking for so it can do a save by thrusters?

17 August 2011 - failure due to an issue with programming around Gyro limitation (Clearly a case to be argued about changing out the gyro for one that does not have the weakness). The thrusters would not have helped. Actually, it burned all it's fuel.

6 August 2012 - FOD, clogged line. Chances of the thrusters also working?

« Last Edit: 12/10/2012 06:39 pm by kevin-rf »
If you're happy and you know it,
It's your med's!

Offline Chris Bergin

Re: Fixing Briz
« Reply #6 on: 12/10/2012 06:39 pm »
They always said with shuttle that redesigning/mods always risked making the issue bigger, so I'd go with better QA.
Support NSF via L2 -- Help improve NSF -- Site Rules/Feedback/Updates
**Not a L2 member? Whitelist this forum in your adblocker to support the site and ensure full functionality.**

Offline Danderman

  • Extreme Veteran
  • Senior Member
  • *****
  • Posts: 10288
  • Liked: 699
  • Likes Given: 723
Re: Fixing Briz
« Reply #7 on: 12/10/2012 07:08 pm »
Btw a list of Briz failures over the last few years:



14 March 2008 - Ruptured plumbing, you can not continue to use the system after that.

6 August 2012 - FOD, clogged line. Chances of the thrusters also working?



A well design integrated fuel system may have saved these two missions. For example, looking at the Soyuz spacecraft prop system, there are capabilities for completing entire missions missing the main engine.

Offline Danderman

  • Extreme Veteran
  • Senior Member
  • *****
  • Posts: 10288
  • Liked: 699
  • Likes Given: 723
Re: Fixing Briz
« Reply #8 on: 12/10/2012 07:09 pm »
They always said with shuttle that redesigning/mods always risked making the issue bigger, so I'd go with better QA.

I suspect that if the same engine failed two or three times during Shuttle missions, causing LOM, then redesigns would be in order.

Offline kevin-rf

  • Elite Veteran
  • Senior Member
  • *****
  • Posts: 8823
  • Overlooking the path Mary's little Lamb took..
  • Liked: 1318
  • Likes Given: 306
Re: Fixing Briz
« Reply #9 on: 12/10/2012 07:16 pm »
A well design integrated fuel system may have saved these two missions. For example, looking at the Soyuz spacecraft prop system, there are capabilities for completing entire missions missing the main engine.

Raised eyebrow... considering the verniers run off the same turbo pump as the main engine, how? I suspect the gravity losses may eat you alive.

Or are you referring to the manned Soyuz spacecraft and not the rocket?
« Last Edit: 12/10/2012 07:17 pm by kevin-rf »
If you're happy and you know it,
It's your med's!

Offline Stan Black

  • Senior Member
  • *****
  • Posts: 3135
  • Liked: 377
  • Likes Given: 228
Re: Fixing Briz
« Reply #10 on: 12/10/2012 07:17 pm »
 As far as I understand… in 1999 there was two failures of Proton-K due second stage engines. The first return to service was quick and followed shortly after by another failure. The failures were from old rockets. Turns out they already had a plan in place to enhance these engines for the Proton-M, and these improvements would also later be used in Proton-K. They just got forced to introduce them earlier, and re-fit already manufactured rockets.

 I wonder if the same thing is happening here. Briz-M is already to be improved for phase IV, the first having flown for Intelsat-22?

 But removing pages from the website; then giving quick explanations for the failures does not help.

Offline zaitcev

  • Full Member
  • ****
  • Posts: 581
    • mee.nu:zaitcev:space
  • Liked: 3
  • Likes Given: 3
Re: Fixing Briz
« Reply #11 on: 12/10/2012 08:02 pm »
6 August 2012 - FOD, clogged line. Chances of the thrusters also working?
The clogged or folded pressurization line was the topic of much speculation on forums, because the failed stage was worked upon and the line was replaced. Allegedly photos taken before the closeout showed undercomplement number of fasteners installed. However, IIRC, the final conclusion unexpectedly fingered an unnamed component made in Omsk. Allegedly, Omsk people did a quality job, but they understood the intent of designers improperly and so their part was materially different from one made in Fili. Several Briz-M missions flew with Omsk-made parts, but they were not pushed as hard and so the difference did not cause a failure. Fili was responsible for QC but it never occured for them to check the the specific deviation that occured. Or so I heard.

Offline Prober

  • Senior Member
  • *****
  • Posts: 10348
  • Save the spin....I'm keeping you honest!
  • Nevada
  • Liked: 721
  • Likes Given: 729
Re: Fixing Briz
« Reply #12 on: 12/10/2012 08:06 pm »
Well do we know what's going on at Khrunichev? For some reason the Fregat upper stage build by Lavochikin, which uses an engine with more or less the same parts and design, never had any in flight failures since its first flight in 2000 (and only one small ground processing issue that led to a slightly off course mission in 2009). Why? QA issues? Or just that a space tug with a pump fed engine that must work for 9 hours + is just difficult to work with high reliability?

You forgot about Lavochikin's work with Phobos Grunt.
2017 - Everything Old is New Again.
"I fear all we have done is to awaken a sleeping giant..." --Isoroku Yamamoto

Offline Rocket Science

  • Senior Member
  • *****
  • Posts: 10586
  • NASA Educator Astronaut Candidate Applicant 2002
  • Liked: 4548
  • Likes Given: 13523
Re: Fixing Briz
« Reply #13 on: 12/10/2012 08:16 pm »
A redesign for the sake of a redesign is a waste of resources. Then what’s to say if your redesign has failures due to QC. Start with basics of QC on the existing design and go from there...
"The laws of physics are unforgiving"
~Rob: Physics instructor, Aviator

Offline Galactic Penguin SST

Re: Fixing Briz
« Reply #14 on: 12/10/2012 08:34 pm »
You forgot about Lavochikin's work with Phobos Grunt.

Well a complex Phobos sample return mission is much more complex than "just" an upper stage.... (remember the software loop that the Russians think P-G got stuck on?)
Astronomy & spaceflight geek penguin. In a relationship w/ Space Shuttle Discovery. Current Priority: Chasing the Chinese Spaceflight Wonder Egg & A Certain Chinese Mars Rover

Offline kevin-rf

  • Elite Veteran
  • Senior Member
  • *****
  • Posts: 8823
  • Overlooking the path Mary's little Lamb took..
  • Liked: 1318
  • Likes Given: 306
Re: Fixing Briz
« Reply #15 on: 12/11/2012 01:16 pm »
It's not just rockets Russia is have quality problems with, http://www.flightglobal.com/blogs/the-dewline/2012/12/russias-su-34-fleet-found-to-h.html
 
If you're happy and you know it,
It's your med's!

Offline spectre9

  • Senior Member
  • *****
  • Posts: 2403
  • Australia
  • Liked: 42
  • Likes Given: 68
Re: Fixing Briz
« Reply #16 on: 12/11/2012 01:49 pm »
Aerospace in Russia is hitting a wall it seems.

Soviet technology has lasted quite a while but now it's all starting to break down and lack of new investments are showing through.

I voted for better QA but that's because Proton is on the way out anyway.

Angara with a hydrolox upper stage is where Russia wants to go. Getting that right is important. If it makes it through development. Have we even seen Soyuz 2.1v yet? I know it hasn't launched but has it been seen in public?

Offline DFSL

  • Member
  • Posts: 32
  • Liked: 0
  • Likes Given: 0
Re: Fixing Briz
« Reply #17 on: 12/11/2012 02:47 pm »
Have we even seen Soyuz 2.1v yet? I know it hasn't launched but has it been seen in public?

Erm... There were a couple of threads at this very forum showing pictures of the engine tests and the first rocket being fit-checked at its launchpad. Maybe you didn't see them?

Constant quality control issues seem to plague the Russian industry.

Offline russianhalo117

  • Global Moderator
  • Senior Member
  • *****
  • Posts: 8755
  • Liked: 4672
  • Likes Given: 768
Re: Fixing Briz
« Reply #18 on: 12/11/2012 03:25 pm »
Aerospace in Russia is hitting a wall it seems.

Soviet technology has lasted quite a while but now it's all starting to break down and lack of new investments are showing through.

I voted for better QA but that's because Proton is on the way out anyway.

Angara with a hydrolox upper stage is where Russia wants to go. Getting that right is important. If it makes it through development. Have we even seen Soyuz 2.1v yet? I know it hasn't launched but has it been seen in public?
It is more an affect of the industries ratio of increasing retirement of senior knowledge to the use of recruitment and retention of green engineers/employees without experience. Their employees are retiring too fast to allow proper training of their replacements and that is serious problem.

Offline Danderman

  • Extreme Veteran
  • Senior Member
  • *****
  • Posts: 10288
  • Liked: 699
  • Likes Given: 723
Re: Fixing Briz
« Reply #19 on: 12/14/2012 06:18 pm »
A less radical approach to fixing Briz would be to adopt a vehicle health management system that can assess the condition of the stack, and while shutting down the main engine, use the settling thrusters to generate additional Delta-V, if this can be done safely (ie the stack is stable and the main engine is not exploding).

Of course, it would be super if those settling thrusters could be plumbed to the main prop tanks, with some sort of pyro valve installed to make the connection, in the event of a main engine failure, but that might be asking too much. Without access to the main prop tank, the settling thrusters probably have no more than 50 kg of prop to expend.  However, saving the prop in the satellite is worth more than gold, per kilo saved.


« Last Edit: 12/14/2012 06:18 pm by Danderman »

Tags:
 

Advertisement NovaTech
Advertisement Northrop Grumman
Advertisement
Advertisement Margaritaville Beach Resort South Padre Island
Advertisement Brady Kenniston
Advertisement NextSpaceflight
Advertisement Nathan Barker Photography
1