June 16th
The confidence level in the new November 2018 date for the first launch of SLS (EM-1) is only 70%. This means that the project has about a 1-in-3 chance of slipping to 2019 or later, assuming no issues not already worked into the estimate crop up.The project was started in 2011, and the 2010 NASA Authorization Act required SLS to launch by 2016. It is now four years later, and the likely launch date for EM-1 has slipped to 2018 or later, a slip of two years in the first launch of SLS. That’s one year of schedule slippage for every two years that the project has existed. If the SLS schedule continues to slip at this rate over the next four years, the date of the first SLS launch will slip from 2018 to 2020. And then from 2018 to 2020, SLS will slip one more year or so before finally launching for the first time somewhere in the 2021-2022 timeframe.
Quote from: Jim on 11/08/2021 07:35 pmJune 16thWhat year?Well, it COULD slip a lot...
Just did a quick linear regression line plot on the napkin, looks like the announced date and launch date line intersect somewhere around first half of 2022. I'll just go with April 2nd, 2022 then.
An ABC establishes and documents an integrated set of project requirements, cost, schedule, technical content, and an agreed Joint Cost and Schedule Confidence Level that forms the basis for NASA’s commitment to the Office of Management and Budget and Congress. The original 2014 SLS ABC established a goal to launch in December 2017 and a commitment to launch by November 2018. The SLS and EGS Programs were rebaselined in early 2020 to a November 2021 Artemis I ABC launch date. This assessment did not include COVID-19 impacts, as it occurred prior to the onset of the pandemic. Despite missing Artemis I’s revised ABC launch date of November 2021, ESD officials are confident the integrationand launch will be completed in spring 2022, with a higher probability of launch—in our [OIG's] estimation—by summer 2022.As a result of [Green Run abort] delays, the COVID-19 pandemic, multiple weather events, and the 10 months required for integration and testing, Artemis I will not be ready to launch until at least late February 2022, 3 months after its ABC launch readiness date [from early 2020, or around 3.3 years after its 2014 ABC date] .EGS Program schedules and a June 2021 HEOMD Schedule Risk Analysis (SRA) cite a risk-informed launch readiness date of mid-April 2022. In our judgment, the Agency is on track to launch Artemis I by summer 2022. While first-time integration issues may cause additional delays, NASA currently reports no remaining major issues.
Quote from: tenkendojo on 11/08/2021 08:02 pmJust did a quick linear regression line plot on the napkin, looks like the announced date and launch date line intersect somewhere around first half of 2022. I'll just go with April 2nd, 2022 then.I look at this one and I have to pull a 'Price is Right' bid...April 1st.nuff said.
Quote from: Jim on 11/08/2021 07:35 pmJune 16thWonder if that was informed by the OIG report (which I assume you could have been privy of before its public release)?
When, if ever, will NASA and NG revisit the SRB stack time limit? We know from the earlier discussion that the SRBs use a pressure-sensitive adhesive (PSA) as part of the seal between segments, and the PSA was initially rated to last for one year from time of stacking. That time expires in early January 2022, but NG engineers re-analyzed the tests and inspections done during stacking and recommended that the time could be extended.Did NASA ever formally accept this recommendation? If so, how long is the extension?
Quote from: DanClemmensen on 11/15/2021 04:43 pmWhen, if ever, will NASA and NG revisit the SRB stack time limit? We know from the earlier discussion that the SRBs use a pressure-sensitive adhesive (PSA) as part of the seal between segments, and the PSA was initially rated to last for one year from time of stacking. That time expires in early January 2022, but NG engineers re-analyzed the tests and inspections done during stacking and recommended that the time could be extended.Did NASA ever formally accept this recommendation? If so, how long is the extension?The SRB life was extended by six months.https://www.nasaspaceflight.com/2021/09/first-artemis-1-integrated-tests/"With the projection that the soonest everything could be ready to launch Artemis 1 moving into January, the SLS Program and Solid Rocket Booster (SRB) prime contractor Northrop Grumman has completed an analysis of the amount of time the SRBs can be stacked. The generic limit for the Boosters is a maximum of 12 months, but additional measurements were taken during Booster stacking operations early in 2021 and the analysis using that data says the limit can be extended another six months for the Artemis 1 Boosters."
Quote from: Steven Pietrobon on 11/18/2021 06:47 amQuote from: DanClemmensen on 11/15/2021 04:43 pmWhen, if ever, will NASA and NG revisit the SRB stack time limit? We know from the earlier discussion that the SRBs use a pressure-sensitive adhesive (PSA) as part of the seal between segments, and the PSA was initially rated to last for one year from time of stacking. That time expires in early January 2022, but NG engineers re-analyzed the tests and inspections done during stacking and recommended that the time could be extended.Did NASA ever formally accept this recommendation? If so, how long is the extension?The SRB life was extended by six months.https://www.nasaspaceflight.com/2021/09/first-artemis-1-integrated-tests/"With the projection that the soonest everything could be ready to launch Artemis 1 moving into January, the SLS Program and Solid Rocket Booster (SRB) prime contractor Northrop Grumman has completed an analysis of the amount of time the SRBs can be stacked. The generic limit for the Boosters is a maximum of 12 months, but additional measurements were taken during Booster stacking operations early in 2021 and the analysis using that data says the limit can be extended another six months for the Artemis 1 Boosters."In other words good to go till July/early August. So if something causes a slip past August, it will be not just a Q4 2022 date but somewhere in 2023 due to losing 6+ months to de-stack and re-stack.
April or May 2022.
Quote from: Mr. Scott on 11/08/2021 11:48 pmSpace.com article on October 22nd, 2021: forecasted launch date... February 12th 2022 (estimated to be 113 days between news/forecast). https://www.space.com/nasa-sls-megarocket-artemis-1-moon-launch-february-2022Estimated forecast in news (113 days) x Euler's number (e = 2.718281828459045235360287471352662497757247093699959574966967627724076630353547594571382178525166427427466 ...) = 307 daysPredicted date of launch: Thursday, August 25, 2022 which is Burger Day, National Banana Split Day as well as Kiss-and-Make-Up Day. Also occurs during Cat 5 Hurricane Ian.The moon phase will be near a new moon. So, a very challenging flight around the moon given the orbital position relative to the Earth's magnetic field/bow shock.For more digits of Euler's number (e), please visit the NASA Goddard website link at:https://apod.nasa.gov/htmltest/gifcity/e.1milCurrently sticking with my original forecast from last November 2021. Currently +/- 12 hours, but still ~August 25th, 2022 12:00 ZULU time during a Cat V hurricane. Going to squeak this one in there.
Space.com article on October 22nd, 2021: forecasted launch date... February 12th 2022 (estimated to be 113 days between news/forecast). https://www.space.com/nasa-sls-megarocket-artemis-1-moon-launch-february-2022Estimated forecast in news (113 days) x Euler's number (e = 2.718281828459045235360287471352662497757247093699959574966967627724076630353547594571382178525166427427466 ...) = 307 daysPredicted date of launch: Thursday, August 25, 2022 which is Burger Day, National Banana Split Day as well as Kiss-and-Make-Up Day. Also occurs during Cat 5 Hurricane Ian.The moon phase will be near a new moon. So, a very challenging flight around the moon given the orbital position relative to the Earth's magnetic field/bow shock.For more digits of Euler's number (e), please visit the NASA Goddard website link at:https://apod.nasa.gov/htmltest/gifcity/e.1mil
Quote from: Mr. Scott on 06/26/2022 12:50 amQuote from: Mr. Scott on 11/08/2021 11:48 pmSpace.com article on October 22nd, 2021: forecasted launch date... February 12th 2022 (estimated to be 113 days between news/forecast). https://www.space.com/nasa-sls-megarocket-artemis-1-moon-launch-february-2022Estimated forecast in news (113 days) x Euler's number (e = 2.718281828459045235360287471352662497757247093699959574966967627724076630353547594571382178525166427427466 ...) = 307 daysPredicted date of launch: Thursday, August 25, 2022 which is Burger Day, National Banana Split Day as well as Kiss-and-Make-Up Day. Also occurs during Cat 5 Hurricane Ian.The moon phase will be near a new moon. So, a very challenging flight around the moon given the orbital position relative to the Earth's magnetic field/bow shock.For more digits of Euler's number (e), please visit the NASA Goddard website link at:https://apod.nasa.gov/htmltest/gifcity/e.1milCurrently sticking with my original forecast from last November 2021. Currently +/- 12 hours, but still ~August 25th, 2022 12:00 ZULU time during a Cat V hurricane. Going to squeak this one in there. How do you know when a hurricane is going to come?
https://arstechnica.com/science/2022/06/nasa-aims-to-launch-the-sls-rocket-in-just-2-months/