Quote from: Rocket Science on 05/31/2011 10:29 pmLooks like a scaled up X-37...A bit older, however. Here's Rev 3 of the Platypus IIRC
Looks like a scaled up X-37...
Quote from: Downix on 05/31/2011 11:09 pmQuote from: Rocket Science on 05/31/2011 10:29 pmLooks like a scaled up X-37...A bit older, however. Here's Rev 3 of the Platypus IIRCPlug-Nozzle on that thing? Where did you find the "other" versions? I've only seen the one...Randy
Got to pondering a bit more, the twin 2-seg with a new core stage still seems off, it means more development for the program. Within the RAC-2 studies was one proposal which had Block I as the upper stage w/o the first stage, so, I did a bit of a switcharoo, and instead of developing an AIUS, I had the EDS developed, using the same 8.4m tooling at Michoud as the original plan, added the SRB support beam to the interstage, and viola, we have a core for our twin 2-seg SRB. To speed up development, I did not use the EDS's new insulation, instead utilizing the existing ET orange thermal protection, so the new insulation would need to be added into development later on. In addition, the tank is upside down, with the LOX to the front while for EDS it would be to the rear.This would have been ready to fly in 2008, requiring minimal development. This could loft up to 30.4 tonnes to the ISS. Once the J-2S+ engine was ready, the Block II program begins, substituting the J-2S+ for the SSME. This increases the payload to 36 tonnes to the ISS. When Ares V is ready, swap interstage with one not sporting the SRB support to lighten the load and use the new, non-popcorning insulation, but keep the existing design for crewed launch. Consolidation of manufacturing, tooling, and employees makes it more efficient an operation. This would have reduced the cost to develop the Ares V as well, with the EDS already being 80% completed, and enabled systems testing in the process. When the 5-segment design for SRB was completed, the 2-segment now becomes the 5-segment with the 3 middle pieces eliminated. It would have fulfilled the ESAS CLV requirements, taken less time and money, and have been ready for flight by the required date. No long poles, no costly up-front development, none of that.
I found the one design in the NASA files (Boeing SRB-X), with a dual set of solids and the 2nd stage in the middle, it looked workable.
Quote from: Prober on 06/02/2011 03:43 pmI found the one design in the NASA files (Boeing SRB-X), with a dual set of solids and the 2nd stage in the middle, it looked workable.It was the worse SDLV design ever and a bigger kludged than Ares I. It is not viable
Quote from: Jim on 06/02/2011 04:52 pmQuote from: Prober on 06/02/2011 03:43 pmI found the one design in the NASA files (Boeing SRB-X), with a dual set of solids and the 2nd stage in the middle, it looked workable.It was the worse SDLV design ever and a bigger kludged than Ares I. It is not viableWhen I first saw Ares I the SRB-X was the first thing to go through my mind.I'll admit, the *idea* of Ares I is ok, but it rapidly went overboard.
Quote from: Downix on 06/02/2011 05:03 pmQuote from: Jim on 06/02/2011 04:52 pmQuote from: Prober on 06/02/2011 03:43 pmI found the one design in the NASA files (Boeing SRB-X), with a dual set of solids and the 2nd stage in the middle, it looked workable.It was the worse SDLV design ever and a bigger kludged than Ares I. It is not viableWhen I first saw Ares I the SRB-X was the first thing to go through my mind.I'll admit, the *idea* of Ares I is ok, but it rapidly went overboard.The design may have had merit if it did not need to have a 23MT payload or carry a crew.have commonality with the EDS, and was proposed ten or fifteen years earlier.The biggest problem with it the EELVs already did the exact same job but for lower cost.Another problem growing payload requirements made Ares V loose commonality with Ares I which eliminated it's second purpose to help pay for the HLV.What the whole ESAS architecture needed was to give up on the 1.5 launch architecture and go to two launches.But a vehicle like Ares I could have been successful if it was proposed back in the 80s or 90s and the target payload set to something well within the reach of the existing 4 segment RSRM.
I still say the 1.5 architecture was fundamentally flawed.It put too many requirements on the CaLV causing it to grow into a 188MT monster.Even a 2.5 launch architecture would be easier though a smaller SDLV would be easier to man rate and eliminated the third launch.In my opinion the Apollo mindset was the biggest thing wrong with project Constellation.It was Apollo except the crew rode up on a separate smaller rocket and LOI was moved to the lander.They pretty much threw out all the lessons learn on ISS and the Shuttle.CxP even excluded low risk technologies that could have made it sustainable, such as SEP ferries for cargo ,fuel depots, and L1 staging.
I still say the 1.5 architecture was fundamentally flawed.
It put too many requirements on the CaLV causing it to grow into a 188MT monster.
Even a 2.5 launch architecture would be easier though a smaller SDLV would be easier to man rate and eliminated the third launch.
In my opinion the Apollo mindset was the biggest thing wrong with project Constellation.It was Apollo except the crew rode up on a separate smaller rocket and LOI was moved to the lander.
They pretty much threw out all the lessons learn on ISS and the Shuttle.
CxP even excluded low risk technologies that could have made it sustainable, such as SEP ferries for cargo ,fuel depots, and L1 staging.
It's been a very long time since I've read the original threads on these issues, but wasn't part of the problem that Nasa seriously underestimated the mass of the LSAM in ESAS?
Oh yeah, SEP ferries, fuel depots and L1 staging are low risk technologies - if you can talk the Area 51 alliens into paying for it and managing it and bailing it out when in dire need.
Quote from: renclod on 06/04/2011 11:55 amOh yeah, SEP ferries, fuel depots and L1 staging are low risk technologies - if you can talk the Area 51 alliens into paying for it and managing it and bailing it out when in dire need. The Constellation architecture was fundamentally flawed so much so it cause in insurrection among the engineers.Team direct already showed why the 1.5 architecture was bad and why two smaller HLVs can be better then one monster LV.
It's biggest flaw it was very unimaginative and expensive and inherited all the short comings of the Apollo architecture.
I literally face palmed when I saw Constellation for the first time and knew it was going to fail.
Space exploration is supposed to develop new technologies if you are afraid to trying anything new as in CxP then you are in the wrong business.
As for SEP ferries being low risk they are relatively low risk.DS1 and Smart 1 already proved solar electric to be viable.Telerobotic operations were proven on on ISS resupply with the ATV and missions like Orbital Express.Boeing had them as a key part of their architecture.I consider cryogenic fuel deports even higher risk then SEP tugs but not so high they should be avoided.But ULA says the near zero boil off technology needed for fuel depots is doable.They launch rockets for a living and know more on the subject then the designers of the ESAS architecture.
Team direct already showed why the 1.5 architecture was bad and why two smaller HLVs can be better then one monster LV.
Telerobotic operations were proven on on ISS resupply [...]I consider cryogenic fuel deports even higher risk then SEP tugs but not so high they should be avoided.