If it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?
Good thing, then, that the 5-engine configuration was ditched.
Quote from: Proponent on 03/06/2020 03:48 pmQuote from: SWGlassPit on 03/06/2020 03:42 pmMy understanding is that the challenge in this case was the extremely limited amount of space (in particular, height) available to work with to route all the plumbing and have it work right.If it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?As I understand it, they were already bumping up against how tall they could be (maybe not for Block 1, but for later configurations) and still get out the VAB doors. Keep in mind also that with work moving in parallel on the launcher, changing the height of the engine section would require design changes to literally every single umbilical arm as well, so these basic sizing decisions are made early, and it's enormously expensive and difficult to try to change them later on.
Quote from: SWGlassPit on 03/06/2020 03:42 pmMy understanding is that the challenge in this case was the extremely limited amount of space (in particular, height) available to work with to route all the plumbing and have it work right.If it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?
My understanding is that the challenge in this case was the extremely limited amount of space (in particular, height) available to work with to route all the plumbing and have it work right.
I do wonder if that was part the reasoning behind going with the 4 engine configuration for all blocks. From what I've read, that announcement came as a surprise to many.
Quote from: Proponent on 03/06/2020 03:48 pmIf it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?Constraints.The top of the LH2 tank is limited by the location of the SRB thrust beam. The bottom of the engine section is limited by the Mobile Launcher. These two constraints, combined with the LH2 tank stretch, left a fairly narrow space for the engine section.
C'mon John, you've been kicking around NSF long enough to know this. There is no overall budget for SLS and never has been. So SLS can't be over (or under) budget. NASA spends whatever Congress gives them, sometimes with strict requirements, sometimes ... less strict.
As of August 2018, NASA had obligated approximately $5.3 billion (86 percent) of the $6.2 billion Boeing Stages contract.23 With only $354 million remaining on CLIN 9 for building two Core Stages and the EUS, both NASA and Boeing anticipate exceeding the contract ceiling for CLIN 9 sometime between December 2018 and February 2019—3 years before the current scheduled contract end date of 2021 and prior to delivery of a single Core Stage or completion of the EUS. Federal contracting laws prohibit NASA from exceeding the contract value absent a contract modification. Further, an increase to the contract value without substantially changing the scope of work is considered a cost overrun, a scenario under which NASA would pay a reduced or no award fee on the additional costs. Consequently, NASA and Boeing will need to renegotiate the contract terms, amount of cost overrun, and schedule. Based on our audit work, we expect this next contract modification will require both a major increase in value and an extension of the delivery schedule for the two Core Stages and EUS.
Quote from: jadebenn on 03/06/2020 06:07 pmQuote from: Proponent on 03/06/2020 03:48 pmIf it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?Constraints.The top of the LH2 tank is limited by the location of the SRB thrust beam. The bottom of the engine section is limited by the Mobile Launcher. These two constraints, combined with the LH2 tank stretch, left a fairly narrow space for the engine section.This is why using SRB is dumb, it puts severe limit on your options.
Quote from: su27k on 03/07/2020 03:19 amQuote from: jadebenn on 03/06/2020 06:07 pmQuote from: Proponent on 03/06/2020 03:48 pmIf it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?Constraints.The top of the LH2 tank is limited by the location of the SRB thrust beam. The bottom of the engine section is limited by the Mobile Launcher. These two constraints, combined with the LH2 tank stretch, left a fairly narrow space for the engine section.This is why using SRB is dumb, it puts severe limit on your options.Though you have to use SRB's when LH2 is your fuel. So unless you replace LH2 with some other fuel, like methane for instance, you have to use SRB's.
How much does a SLS cost to launch? The more I read about it the more confused I get, the number ranges anywhere from 800 million to 2 billion. Which number is the correct one?
At an estimated cost of over $2 billion per launch for the SLS once development is complete...
Quote from: jadebenn on 03/06/2020 02:06 pmQuote from: Proponent on 03/06/2020 01:55 pmI see just two difference between Stumpy and what NASA now calls Block 1: Block 1 has four rather than three RS-25's, and Block 1 has a slightly modified Delta IV upper stage.The main difference is that Block 0 is essentially one of DIRECT's Jupiter rockets (boy, haven't heard that name in a while), so no core stretch. This also meant a less-compact engine section, and (most likely) less-thick tank walls, which would have avoided a lot of the issues that plagued core stage development.However, the strike against it was that it had no evolution path. You'll notice that the "Block I" depicted here essentially requires replacement of the entire core. In all likelihood, such an effort would have never happened. Its future would more uncertain than the current Block 2 SLS is.Because of differing loads, Stumpy's unstretched core still would have been fundamentally different from the Shuttle's ET.QuoteI'd say "Block I" is much closer to the modern Block 1. It's just got one engine too many and one ICPS too few.Yes, but the old "Block 1" is still an EUS and advanced boosters away from the old "Block 3."EDIT: "and" to "an" in final sentence
Quote from: Proponent on 03/06/2020 01:55 pmI see just two difference between Stumpy and what NASA now calls Block 1: Block 1 has four rather than three RS-25's, and Block 1 has a slightly modified Delta IV upper stage.The main difference is that Block 0 is essentially one of DIRECT's Jupiter rockets (boy, haven't heard that name in a while), so no core stretch. This also meant a less-compact engine section, and (most likely) less-thick tank walls, which would have avoided a lot of the issues that plagued core stage development.However, the strike against it was that it had no evolution path. You'll notice that the "Block I" depicted here essentially requires replacement of the entire core. In all likelihood, such an effort would have never happened. Its future would more uncertain than the current Block 2 SLS is.
I see just two difference between Stumpy and what NASA now calls Block 1: Block 1 has four rather than three RS-25's, and Block 1 has a slightly modified Delta IV upper stage.
I'd say "Block I" is much closer to the modern Block 1. It's just got one engine too many and one ICPS too few.
This is why Obama wanted to develop large hydrocarbon engine first and postpone superheavy development by 5 years, it's not a good idea to use LH2 in your first stage, and US was badly behind in hydrocarbon engine technology back then, of course congress had other ideas...
Was Stumpy Direct’s J-130? I thought Stumpy was smaller, but the J-130 was essentially an ET with 3 engines in the base
Quote from: su27k on 03/07/2020 10:54 amThis is why Obama wanted to develop large hydrocarbon engine first and postpone superheavy development by 5 years, it's not a good idea to use LH2 in your first stage, and US was badly behind in hydrocarbon engine technology back then, of course congress had other ideas...Nothing restricted the Obama administration from spending SLS funds on a hydrocarbon engine (see F-1B for advanced boosters...they never pulled the trigger).
(1) IN GENERAL.—The Administrator shall, as soon as prac- ticable after the date of the enactment of this Act, initiate development of a Space Launch System meeting the minimum capabilities requirements specified in subsection (c).(2) MODIFICATION OF CURRENT CONTRACTS.—In order to limit NASA’s termination liability costs and support critical capabilities, the Administrator shall, to the extent practicable, extend or modify existing vehicle development and associated contracts necessary to meet the requirements in paragraph (1), including contracts for ground testing of solid rocket motors, if necessary, to ensure their availability for development of the Space Launch System.
Quote from: Coastal Ron on 03/07/2020 04:42 amQuote from: su27k on 03/07/2020 03:19 amQuote from: jadebenn on 03/06/2020 06:07 pmQuote from: Proponent on 03/06/2020 03:48 pmIf it was a matter of height, why wasn't the height increased a bit more? Was there some constraint that made this impractical, or was the difficulty of working with the height as is not recognized?Constraints.The top of the LH2 tank is limited by the location of the SRB thrust beam. The bottom of the engine section is limited by the Mobile Launcher. These two constraints, combined with the LH2 tank stretch, left a fairly narrow space for the engine section.This is why using SRB is dumb, it puts severe limit on your options.Though you have to use SRB's when LH2 is your fuel. So unless you replace LH2 with some other fuel, like methane for instance, you have to use SRB's.Delta IV Heavy says...Hi!
Which proves Coastal Ron’s point. Using LH2 in the booster stage requires 3 massive cores to lift a mere 26 metric tons into LEO. LH2 is inefficient for a booster stage.
Quote from: ncb1397 on 03/07/2020 07:15 pmQuote from: su27k on 03/07/2020 10:54 amThis is why Obama wanted to develop large hydrocarbon engine first and postpone superheavy development by 5 years, it's not a good idea to use LH2 in your first stage, and US was badly behind in hydrocarbon engine technology back then, of course congress had other ideas...Nothing restricted the Obama administration from spending SLS funds on a hydrocarbon engine (see F-1B for advanced boosters...they never pulled the trigger). But the timetable imposed by Congress ruled out hydrocarbon engines for SLS's core.