Quote from: Comga on 08/24/2012 10:33 pm1-Is this correct, enthusiatic loose interpretation, or just more blather?2-It could be hoped that JPL is held to the cost cap, but I doubt it. We could start a poll on our guesses for the final cost, $400-450M, $450-500M, up to >$1G. 1-It is mostly correct. Note that he's not talking about the technology, he's essentially talking about the team of EDL experts. Most of those people were going to be out of a job. Now many of them will work on InSight. Not all, because InSight is less sophisticated. But this is an important resource to preserve.2-What is the basis for your skepticism? This is a proven lander design, and the blueprints already exist. The instruments are being provided by European sources. Note that both GRAIL and InSight were selected because of a belief that their cost estimates were sound (and both were based upon existing spacecraft). GRAIL actually came in under budget. Can you cite a single Discovery mission that doubled in price?
1-Is this correct, enthusiatic loose interpretation, or just more blather?2-It could be hoped that JPL is held to the cost cap, but I doubt it. We could start a poll on our guesses for the final cost, $400-450M, $450-500M, up to >$1G.
It could be hoped that JPL is held to the cost cap, but I doubt it. We could start a poll on our guesses for the final cost, $400-450M, $450-500M, up to >$1G.
LM is building the spacecraft vs JPL
2-What is the basis for your skepticism? This is a proven lander design, and the blueprints already exist. The instruments are being provided by European sources. Note that both GRAIL and InSight were selected because of a belief that their cost estimates were sound (and both were based upon existing spacecraft). GRAIL actually came in under budget. Can you cite a single Discovery mission that doubled in price?
Finally, it strikes me as totally insane to reward JPL for delivering MSL
Further, there is huge risk associated with those contributed instruments. NASA/JPL have no leverage over the providers to deliver on-time and with the necessary performance. Since instruments habitually miss schedule targets,
Thus a minimum mission now would be in the $530M - $610M range, not counting for inflation. The previous concerns on cost credibility were justified.
at least we still get pretty rust-colored pictures of a rocky desert.
Quote from: Blackstar on 08/25/2012 12:48 pm2-What is the basis for your skepticism? This is a proven lander design, and the blueprints already exist. The instruments are being provided by European sources. Note that both GRAIL and InSight were selected because of a belief that their cost estimates were sound (and both were based upon existing spacecraft). GRAIL actually came in under budget. Can you cite a single Discovery mission that doubled in price? Where to start ...? Phoenix redux missions have been proposed under previous Mars Scout ($475M cap in FY2007) and New Frontiers ($650M cap in FY2009) and rejected by HQ due to cost credibility concerns. Estimates of the original PHX mission range from $420M to $480M but do not include any of the cost associated with the inherited hardware from the '01 Lander nor the value of the engineering effort (design, analyses, documentation, etc) that would have gone along with developing the hardware designs. Given the overall dollars spent on the '01 effort that covered the orbiter and the lander was in the neighborhood of $220M, one could easily peg that total value in the $110 -$130M range. As the '01 was done in the FBC era, corners were cut then that, in the current environment, would never be tolerated. Thus a minimum mission now would be in the $530M - $610M range, not counting for inflation. The previous concerns on cost credibility were justified. Yes, the Insight instruments are contributed but that contribution doesn't come anywhere close to shaving off $100M - $175M in cost (not counting the 30% reserves that Insight has to demonstrate). Further, there is huge risk associated with those contributed instruments. NASA/JPL have no leverage over the providers to deliver on-time and with the necessary performance. Since instruments habitually miss schedule targets, the whole program is at risk of delay and missing the planned launch window. Just like MSL, they will face a two-year delay in launch if they fail to meet the planned schedule resulting in even more additional costs. Finally, it strikes me as totally insane to reward JPL for delivering MSL two years late and more than $1.6B over cost by giving them yet another Mars lander project, particularly when they have been promised another Mars mission (directed mission) scheduled for launch in the 2018 timeframe. MSL ate the Mars Scout program and now the Mars science community and JPL are about to eat the Discovery program as well. But hey, at least we still get pretty rust-colored pictures of a rocky desert.
Discovery is cost-capped. If the mission costs as much as you claim it must, then it already exceeds the cost cap. So you're essentially saying that NASA picked a mission that exceeds the cost cap and is lying about it. That just isn't a credible claim.
R&D for the lander is already paid for. You don't need to be re-counting that cost as part of any new effort to re-use the lander.
History suggests that a mars lander cannot be delivered for less than $500M. JPL has demonstrated that they cannot control costs associated with Mars landers (MER, MSL). Thus I am questioning how NASA can justify, based on cost credibility, the selection of another Mars lander, led by JPL, under even tighter cost caps than previous missions.
Mars Pathfinder?
Insight will exceed its $425M cost cap, of that I am confident. Only question is by how much. I am predicting now that it launches at a minimum cost of $575M but I wouldn't be surprised to see it top $650M. Just my $0.02.
JPL has demonstrated that they cannot control costs associated with Mars landers (MER, MSL).
MER, when approved for flight, was originally costed at $688 million. The actual cost to the end of the 90-Sol mission was $800 million, or $112 million, or a totally whopping, unacceptable, er... 16% cost overrun. Now, given the horrible performance of MER at achieving the 90-Sol mission, I can see how this huge 16% cost overrun might be considered a basis for never giving JPL another Mars mission.
Finally, your response says nothing about MSL which most represents the state of JPL and Mars missions as the backdrop to Insight.
The second facility instrument would measure basic weather conditions -- temperature, pressure, wind speed -- so that the noise from the local atmospheric conditions can be removed from the seismometer's readings. The weather readings also will be useful meteorological data in themselves.