Remember that 10.5mm wide-angle lens that produced those great photos during the STS-134 and STS-135 EVAs? Well, that same lens will be going outside tomorrow.
http://spaceflight.nasa.gov/gallery/images/shuttle/sts-134/lores/iss028e005676.jpgSpacewalkers Suni & Aki will egress the A/L (Airlock) hatch at ~8:15 AM EDT/12:15 PM GMT, for an outside duration of ~6h 30m (i.e., ingress ~2:45 PM EDT/6:45 PM GMT). EVA-18 objectives are:
· Connect & route two power cables (#651, #413) for the yet-to-arrive Russian MLM (Multipurpose Laboratory Module) between the FGB & US Segment (future Russian EVA will complete the cable layouts and provide US power to MLM & SM via all 4 MBSUs [Main Bus Switching Units], instead of current configuration where only two are used to power SM)
· Remove the failed MBSU1 and replace it with the spare MBSU,
· Install failed MBSU1 in stbd ESP-1 FSE (External Stowage Platform 1 Flight Support Equipment)
· Remove failed SSRMS Boom B CLPA (Camera, Light, Pan/Tilt Assembly) and replace with spare CLPA
Get-aheads (time permitting) are:
· Install PMA-2 MMOD/thermal cover
· Remove & replace MBS (Mobile Base System) mast CLPA
· Replace JEF VE (JEM Exposed Facility Vision Equipment) fwd camera+light
· Troubleshoot FGB PDGF (Power & Data Grapple Fixture)
· Reconfigure EVA tools (WIF/Worksite Interface Fixture Extender).