ET-123 in Building 103, Cell 2.
Flange foam removal: LH2 flange gross foam removal continues: Panel 5 is 100 % complete; Panel 4 is 100% complete; Panel 3 is at 60% complete and Panel 2 at 50% complete.  Panels 4 and 5 are undergoing residue removal and Panel 4 is at 40% and Panel 5 is at 20% residue removal.
Ice Frost Ramp Removal: Ice frost ramp removal is in work. Stations 1270 went through DCMA for inspection. Stations 1151, 1205 and 1270 have been removed and are awaiting QC/ DCMA inspection.

Offline Avron

  • Canadian Member
  • Senior Member
  • *****
  • Posts: 4920
  • Liked: 150
  • Likes Given: 152
RE: ET-123 latest
« Reply #1 on: 01/27/2006 11:31 PM »
Quote
Chris Bergin - 27/1/2006  11:39 AM

ET-123 in Building 103, Cell 2.
Flange foam removal: LH2 flange gross foam removal continues: Panel 5 is 100 % complete; Panel 4 is 100% complete; Panel 3 is at 60% complete and Panel 2 at 50% complete.  Panels 4 and 5 are undergoing residue removal and Panel 4 is at 40% and Panel 5 is at 20% residue removal.
Ice Frost Ramp Removal: Ice frost ramp removal is in work. Stations 1270 went through DCMA for inspection. Stations 1151, 1205 and 1270 have been removed and are awaiting QC/ DCMA inspection.

Question, any idea why the Ice frost ramps are comming off. I was under the impression they where to stay?

Offline Flightstar

  • Lurking around OPF High Bay 2
  • Full Member
  • ****
  • Posts: 1870
  • KSC, Florida
  • Liked: 11
  • Likes Given: 5
RE: ET-123 latest
« Reply #2 on: 01/31/2006 01:30 AM »
I think it's the way they've worded it. They aren't removing it all, I assume. just shortening it down.

Offline Mark Dave

  • Full Member
  • ****
  • Posts: 1104
  • Ruined
  • Liked: 2
  • Likes Given: 0
Re: ET-123 latest
« Reply #3 on: 03/05/2007 10:25 PM »
Are there any processing photos of the new ETs?

Tags: